Editor: I. Mallikarjuna Sharma Volume 11: 15-31 March 2015 No. 5-6
Martyrs memorial special issue of 15-31 March 2015 paying tributes to Bhagat Singh and other comrades.
Martyrs memorial special issue of 15-31 March 2015 paying tributes to Bhagat Singh and other comrades.
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
(20<strong>15</strong>) 1 LAW Quake Outcasts v. Minister for Canterbury Earthquake Recovery [NZ-SC: Court Opinion] F-<strong>15</strong>7<br />
of land damage, the cost-effectiveness and social impacts<br />
of land remediation”. 67 The zones were labelled<br />
green, orange, red and white. 68<br />
[50] The green zones covered areas where there<br />
were “no significant issues which prevent<br />
rebuilding in those areas, based on current<br />
knowledge of seismic activity”. 69 The red zones<br />
were reserved for areas where “rebuilding may not<br />
occur in the short-to-medium term because the land is<br />
damaged beyond practical and timely repair”. 70 It was<br />
noted that most buildings in the red zones were<br />
rebuilds, that the areas were at risk of further<br />
danger from low-level shaking, floods or spring<br />
tides and that infrastructure needed to be rebuilt. 71<br />
[51] The orange zones were areas where further<br />
work was required to determine if rebuilding<br />
could occur in the short-to-medium term. 72 The<br />
white zones included the Port Hills area where<br />
the 13 June 20<strong>11</strong> earthquake had caused further<br />
extensive damage necessitating further<br />
assessment. 73<br />
[52] The Brownlee paper outlined the criteria<br />
used by the Committee for determining those<br />
areas where rebuilding was unlikely to be<br />
practical over the short-to-medium term as<br />
follows: 74<br />
(a) There is area-wide land damage, thereby<br />
implying some sort of area-wide solution;<br />
AND<br />
(b) An engineering solution to remediate the<br />
land damage would:<br />
67 At [10].<br />
68 The decisions taken by the Committee did not deal with<br />
the Central Business District as that was to be addressed<br />
as part of the “Central City Plan”: see at [2.2] of the<br />
recommendations.<br />
69 At [10](a).<br />
70 At [10](c).<br />
71 At [10](c).<br />
72 At [10](b).<br />
73 At [10](d).<br />
74 At [36] (emphasis in the original).<br />
♦ be uncertain in terms of the detailed design,<br />
its success and its possible commencement,<br />
given the ongoing seismic activity, AND<br />
♦ be disruptive for landowners, as the<br />
commencement date is uncertain (both in<br />
terms of confidence in the land settling<br />
sufficiently to begin remediation and the<br />
need to sequence the many areas where<br />
remediation would be required), and the<br />
length of time they would need to be out<br />
of their homes to allow remediation to<br />
occur and new homes built, AND<br />
♦ not be timely: for example there is also<br />
substantial replacement of infrastructure<br />
required and/or the land level needs to be<br />
significantly lifted effectively requiring<br />
work equivalent to the development of a<br />
new subdivision, and would probably lead<br />
to significant social dislocation for those<br />
communities in the short-to-medium term,<br />
AND<br />
♦ not be cost-effective: on a per section basis<br />
the cost of remediation is greater than the<br />
value of the land as shown below:<br />
The EQC contribution to the land remediation<br />
+<br />
The betterment cost (i.e. perimeter treatment and/or<br />
additional raising of the land)<br />
+<br />
Infrastructure removal and replacement costs<br />
If the cost of the above<br />
exceeds the value of the<br />
relevant land the area is<br />
reclassified as a Red Zone<br />
If the cost of the above is<br />
less than the value of the<br />
relevant land then the area<br />
is reclassified as a Green<br />
Zone, but may require<br />
some land repair work<br />
(c) The health or well-being of residents is at risk from<br />
remaining in the area for prolonged periods.<br />
[53] The Brownlee paper went on to say that,<br />
“[i]f these criteria are met, then the government<br />
should consider how it can best support the<br />
recovery in these areas”. 75 It was recognised that,<br />
in some areas of significant land damage, there<br />
may be isolated pockets of land that fared<br />
75 At [37].<br />
99<br />
Law Animated World, <strong>15</strong>-<strong>31</strong> <strong>March</strong> 20<strong>15</strong>