<strong>Earned</strong> <strong>Schedule</strong> – Re-Baseline Example<br />

Real project data – nominal re-baseline<br />

40.00<br />

1. Nominal Re-plan 02 July<br />

Cost and schedule overrun<br />

35.00<br />

Duration (Weeks)<br />

30.00<br />

25.00<br />

20.00<br />

15.00<br />

3. Re-baseline effect<br />

10.00<br />

5.00<br />

0.00<br />

2. <strong>Schedule</strong><br />

delay<br />

01 Jan 29 Jan 26 Feb 26 Mar 30 Apr 28 May 25 Jun 02 Jul 30 Jul 27 Aug<br />

Actual Time (weeks) 0.00 4.00 8.00 12.00 17.00 21.00 25.00 26.00 30.00 34.00<br />

Planned <strong>Schedule</strong> ReBline #1 0.00 4.00 8.00 12.00 17.00 21.00 25.00 26.00 30.00 33.00<br />

Planned <strong>Schedule</strong> cum CBB 0.00 4.00 8.00 12.00 17.00 20.00 20.00 20.00 20.00 20.00<br />

<strong>Earned</strong> <strong>Schedule</strong> cum 0.00 3.84 8.60 12.56 16.87 17.45 17.59 25.91 28.70 33.00<br />

IEAC(t) SPI(t) 20.85 18.60 19.11 20.15 24.07 28.42 33.12 34.50 34.00<br />

EVA-11<br />

Copyright 2006<br />

Jun 12-17, 17, 2006<br />

Lipke & Henderson 71