Earned Schedule Training
Earned Schedule Training Earned Schedule Training
IEAC(t) Predictions using ES Techniques: Weekly Plots of IEAC(t) Late Finish Project Example Commercial IT Infrastructure Expansion Project Phase 1 Earned Schedule, Independent Estimate At Completion (time) - IEAC(t) as at Project Completion: Week Starting 15th July xx Planned Schedule Earned Schedule cum IEAC(t) PD/SPI(t) Duration (Weeks) 40 35 30 25 20 15 10 5 0 Plan Dur wk 20 20 Stop Stop wk wk 19 19 Re-start wk 26 26 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 Actual Time (Weeks) EVA-11 Jun 12-17, 17, 2006 Copyright 2006 Lipke & Henderson 36
IECD Predictions using ES Techniques: Weekly Plots of Independent Estimate of Completion Date Commercial IT Infrastructure Expansion Project Phase 1 Earned Schedule, Independent Estimates of Completion Date (IECD) as at Project Completion: Week Starting 15th July xx Planned Schedule Earned Schedule cum Planned Completion Date Independent Estimate of Completion Date 25 20 Stop wk 19 Stop wk 19 Plan Plan Dur Dur wk wk 20 20 Compl Compl Apr Apr 7 7 28 Jul 90 14 Jul 90 30 Jun 90 16 Jun 90 Duration (Weeks) 15 10 Re-start Re-start wk wk 26 26 02 Jun 90 19 May 90 05 May 90 21 Apr 90 07 Apr 90 24 Mar 90 5 10 Mar 90 24 Feb 90 10 Feb 90 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 27 Jan 90 Actual Time (Weeks) EVA-11 Jun 12-17, 17, 2006 Copyright 2006 Lipke & Henderson 37
- Page 1 and 2: Earned Schedule Training Instructor
- Page 3 and 4: Earned Schedule Training Basic •
- Page 5 and 6: Earned Schedule Training Advanced
- Page 7 and 8: Earned Schedule Training • Statis
- Page 9 and 10: Earned Value Management Schedule In
- Page 11 and 12: EVM Schedule Indicators • SV & SP
- Page 13 and 14: Introduction to Earned Schedule EVA
- Page 15 and 16: Earned Schedule Metrics • Require
- Page 17 and 18: Earned Schedule Indicators • Sche
- Page 19 and 20: SV Comparison 100 80 Early Finish P
- Page 21 and 22: Earned Schedule Predictors • Can
- Page 23 and 24: Earned Schedule Terminology Status
- Page 25 and 26: Earned Schedule Key Points • ES I
- Page 27 and 28: ES Applied to Real Project Data: La
- Page 29 and 30: Early Finish Project: SV($) and SV(
- Page 31 and 32: Prediction Comparisons EVA-11 Jun 1
- Page 33 and 34: IEAC(t) Prediction Comparison Early
- Page 35: EVA-11 Jun 12-17, 17, 2006 IEAC(t)
- Page 39 and 40: 2 My Experience Summarised • Sche
- Page 41 and 42: Earned Schedule Calculator Earned S
- Page 43 and 44: Interpolation Error EVA-11 Jun 12-1
- Page 45 and 46: Interpolation Error $$ ES(calc) BCW
- Page 47 and 48: Interpolation Error • After a few
- Page 49 and 50: BREAK - 15 Minutes EVA-11 Jun 12-17
- Page 51 and 52: Exercise # 1 • Complete Early & L
- Page 53 and 54: ES Exercise - Worksheet Year 01 Yea
- Page 55 and 56: ES Exercise - Answers Year 01 Year
- Page 57 and 58: Early Adopters • EVM Instructors
- Page 59 and 60: Available Resources • PMI-Sydney
- Page 61 and 62: 0,10 0,05 0,00 -0,05 -0,10 -0,15 -0
- Page 63 and 64: Summary - Basic • Derived from EV
- Page 65 and 66: BREAK - 15 Minutes EVA-11 Jun 12-17
- Page 67 and 68: Analysis Tool Demonstration EVA-11
- Page 69 and 70: ES and Re-Baselining EVA-11 Jun 12-
- Page 71 and 72: Earned Schedule - Re-Baseline Examp
- Page 73 and 74: Critical Path Study EVA-11 Jun 12-1
- Page 75 and 76: EVA-11 Jun 12-17, 17, 2006 The Sche
- Page 77 and 78: To further compound schedule comple
- Page 79 and 80: Case Study Project • Commercial s
- Page 81 and 82: Schedule Management • Weekly sche
- Page 83 and 84: • Initial expectation EVA-11 Jun
- Page 85 and 86: The IECD vs Critical Path Predictor
IEAC(t) Predictions using<br />
ES Techniques: Weekly Plots of IEAC(t)<br />
Late Finish Project Example<br />
Commercial IT Infrastructure Expansion Project Phase 1<br />
<strong>Earned</strong> <strong>Schedule</strong>, Independent Estimate At Completion (time) - IEAC(t)<br />
as at Project Completion: Week Starting 15th July xx<br />
Planned <strong>Schedule</strong> <strong>Earned</strong> <strong>Schedule</strong> cum IEAC(t) PD/SPI(t)<br />
Duration (Weeks)<br />
40<br />
35<br />
30<br />
25<br />
20<br />
15<br />
10<br />
5<br />
0<br />
Plan Dur wk 20 20<br />
Stop Stop wk wk 19 19 Re-start wk 26 26<br />
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34<br />
Actual Time (Weeks)<br />
EVA-11<br />
Jun 12-17, 17, 2006<br />
Copyright 2006<br />
Lipke & Henderson 36