Earned Schedule Training
Earned Schedule Training
Earned Schedule Training
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
<strong>Earned</strong> <strong>Schedule</strong> Terminology<br />
Metrics<br />
<strong>Earned</strong> <strong>Schedule</strong><br />
ES cum<br />
ES = C + I number of complete<br />
periods (C) plus an incomplete<br />
portion (I)<br />
Actual Time<br />
AT cum<br />
AT = number of periods executed<br />
<strong>Schedule</strong> Variance<br />
SV(t)<br />
SV(t) = ES - AT<br />
Indicators<br />
<strong>Schedule</strong> Performance<br />
Index<br />
SPI(t)<br />
SPI(t) = ES / AT<br />
To Complete <strong>Schedule</strong><br />
TSPI(t)<br />
TSPI(t) = (PD – ES) / (PD – AT)<br />
Performance Index<br />
TSPI(t) = (PD – ES) / (ED – AT)<br />
Predictors<br />
Independent Estimate<br />
IEAC(t)<br />
IEAC(t) = PD / SPI(t)<br />
at Completion (time)<br />
IEAC(t) = AT + (PD – ES) / PF(t)<br />
EVA-11<br />
Jun 12-17, 17, 2006<br />
Copyright 2006<br />
Lipke & Henderson 24