Question #9<br />

• What does the P-Factor P<br />

help us understand<br />

about project performance?<br />

O How closely the project is following its plan<br />

O Why performance has the tendency to<br />

become less efficient as EV ⇒ BAC<br />

O Improves analysis of true project<br />

accomplishment<br />

O All of the above<br />

EVA-11<br />

Jun 12-17, 17, 2006<br />

Copyright 2006<br />

Lipke & Henderson 141