DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />

PHASE 3B<br />

ITEM DESCRIPTION<br />

QTY UNIT UNIT COST AMOUNT<br />

B12 Retaining Wall and Perimeter Fence of Substation 295 l.m.<br />

Expansion Area - Consisting of Concrete (211kg/cm²),<br />

Reinforcing steel bars Grade 275, Excavation and<br />

backfill, CHB including demolition/restoration works for<br />

the affected portion of the existing retaining<br />

wall/perimeter fence and other incidentals to complete<br />

the work. To include painting of walls and perimeter<br />

fence and affected areas.<br />

B13 69kV Gantry Structure Foundation Consisting of 1 set<br />

concrete (211kg/cm²), Non-shirk Grout, Reinforcing Steel<br />

Bars (Grade 275), Excavation and backfill, Leveling<br />

Concrete (141 kg/cm²) and other incidentals required to<br />

complete the works.<br />

B14 Expansion of Existing Clark 230KV S/S Control 115 sq.m.<br />

House Consisting of architectural, civil, electrical,<br />

mechanical, and finishing works to match the existing. To<br />

include supply of 3-3 tons split air conditioning units,<br />

industrial type exhaust fan, fire detection units to connect<br />

to existing Fire Alarm panel, lights and outlets, wiring and<br />

other accessories and incidentals to complete the work.<br />

To include repainting of Bldg external and affected<br />

areas.<br />

B15 Proposed Clark 230KV S/S Warehouse Consisting of 288 sq.m.<br />

architectural, civil/structural, electrical, and mechanical<br />

works for the construction of steel frame warehouse with<br />

minimum beam height of 6.00 meters. To include supply<br />

and installation of industrial exhaust fans, lighting fixtures<br />

and outlets. Painting of building internal and external.<br />

B16 Fire Water System,<br />

a. Cleaning & Flushing of following existing facilities<br />

1. 100 mm 440 mtrs<br />

2. 50 mm 110 mtrs<br />

3. 40 mm 200 mtrs<br />

4. Assorted sizes to control room, guard house 100 mtrs<br />

and green area<br />

5. Elevated Water Tank 10,000 gal<br />

1 set<br />

b. New Installation of the following<br />

1. 100 mm GI super sched 40 underground line 420 mtrs<br />

2.<br />

with fittings, valves sand beddings and with<br />

protection membrane<br />

Fire hose reel cabinet with 40 mm brass 12 sets<br />

nozzle, 40 mm x 30 mtrs hose, 40 mm brass<br />

valve, fittings, glass, painted gauge #10 metal<br />

sheet and concrete foundation.<br />

3. Road Crossing of Fire water line, include 9 mtrs<br />

cutting, excavation, backfilling, sand bedding<br />

and road concreting<br />

B17 Rehabilitation of Existing Water Well, includes<br />

100 mtrs<br />

suctioning/cleaning of existing water well including use of<br />

equipment (air compressor and other cleaning equipment)<br />

B18 Replacement of Existing Submersible Pump multistage<br />

type, 100 GPM, 95 meters TDH complete with control and<br />

including Pull out of existing and installation of new<br />

submersible pump.<br />

1 unit<br />

Page 10 of 15