BILL OF QUANTITIES
BILL OF QUANTITIES
BILL OF QUANTITIES
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>BILL</strong> <strong>OF</strong> <strong>QUANTITIES</strong><br />
DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />
PHASE 3B<br />
ITEM DESCRIPTION<br />
QTY UNIT UNIT COST AMOUNT<br />
1.0 DETAILED ENGINEERING DESIGN<br />
Complete design of Clark - Mexico 230kV Double Circuit 1 lot<br />
Transmission Line, Expansion of Clark and Mexico<br />
230kV Substations, Expansion of Clark Substation<br />
Control House, and the Proposed Clark Substation<br />
Warehouse in accordance with PEC, IEC, ANSI, NESC,<br />
NBC, NSCP and DPWH Design Standards<br />
Compliance to NGCP requirements for the submission of<br />
factory tests, field tests, manuals, procedures and other<br />
documents for NGCP approval. Coordination and other<br />
requirements to energize the system.<br />
Permits, local and national and payments of fees and<br />
other documents as required to complete the project<br />
Compliance to the COA requirements for the submission<br />
of Detailed unit Cost Analysis of Items as listed in the Bill<br />
of Quantities<br />
Provide assistance in the R.O.W acquisition especially in<br />
the consultation/coordination with the Local Government<br />
Units and Barangay Officials having jurisdiction over the<br />
area that will be affected by the R.O.W. of the<br />
transmission line. Assists CDC on the procedure of<br />
payments and registration of property/ROW acquisition in<br />
accordance with R.A. 8974 and other applicable laws.<br />
Detailed Engineering Design Activities as per section 2 of<br />
scope of work<br />
a. Review of existing information<br />
b. Topographic and Parcellary survey<br />
c. Right of way acquisition<br />
d. Soil and material investigation<br />
e. Hydrological and hydraulic studies<br />
f. Environmental impact assessment (EIA)<br />
g. Detailed design plans and specifications<br />
h. Utility relocation plan<br />
i. Detailed estimate / unit price analysis<br />
j. Drawing submittals<br />
k. Reports<br />
Submit three (3) options of possible transmission line<br />
Alignments with cost benefit analysis, evaluation and<br />
recommendation (NLEX, existing 69 kv corridor, new<br />
route)<br />
2.0 230 Kv TRANSMISSION LINE From Clark S/S to Mexico S/S<br />
Construction of Double Circuit (1 x 410 TSAR) on Steel 35 KM<br />
poles or Steel towers, clearance over roadway as per<br />
PEC, IEC, ANSI, NESC, maximum span is 100 meters<br />
on 43 meter steel poles and 250 meters on 52 meters<br />
steel towers in accordance to the requirements of the<br />
Technical Data Sheet (TDS) and compliance to ATO<br />
requirements.<br />
Page 1 of 15
DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />
PHASE 3B<br />
ITEM DESCRIPTION<br />
QTY UNIT UNIT COST AMOUNT<br />
3.0 CLARK SUBSTATION 230/69kV<br />
A. ELECTRICAL WORKS<br />
Supply, manufacture, factory testing, and furnishing of<br />
labor, equipment, tools and incidental materials for the<br />
delivery, assembly, erection, installation, field testing<br />
commissioning and ready for operation of the following<br />
substation equipment and its associated control and<br />
protection system and accessories<br />
Bay 85 and Bay 86 At Clark 230 kV S/S<br />
A1. Power Transformer 150 MVA Three winding autotransformer<br />
2 sets<br />
type 3-Phase 230/69kV wye-13.8 delta with<br />
neutral earthing resistor class ONAN/ONAF1/ONAF2 ,<br />
complete with all appurtenances, accessories and onload<br />
tap changing mechanism with 16 taps of 0.625%<br />
above and 16 taps of 0.625% below 0 including<br />
paralleling device and control in accordance to the<br />
requirements of the Technical Data Sheet (TDS).<br />
A2. Power Circuit Breaker Dead Tank 230kV, 3-phase, 4 sets<br />
2000A, 40, kA three pole operation, complete with the<br />
required accessories and support structure including<br />
bushing current transformers in accordance to the<br />
requirements of the Technical Data Sheet (TDS).<br />
A3. Power Circuit Breaker Dead Tank 69kV, 3-phase, 6 sets<br />
2000A, 38 kA three pole operation, complete with the<br />
required accessories and bushing current transformer in<br />
accordance to the requirements of the Technical Data<br />
Sheet (TDS).<br />
A4. Ganged Disconnect Switch 230kV, 3-phase, 2000A, 10 sets<br />
40KA equipped with 460 vac 3 phase motor and<br />
manually group operated, complete with the required<br />
accessories in accordance to the requirements of the<br />
Technical Data Sheet (TDS).<br />
A5. Ganged Disconnect Switch 69kV, 3-phase, 2000A, 38 4 sets<br />
kA equipped with earthing blades, 230 vac motor and<br />
manually group operated, complete with the required<br />
accessories in accordance to the requirements of the<br />
Technical Data Sheet (TDS).<br />
A6 Ganged Disconnect Switch 69kV, 3-phase, 2000A, 38 14 sets<br />
kA equipped with, 230 vac motor and manually group<br />
operated, complete with the required accessories in<br />
accordance to the requirements of the Technical Data<br />
Sheet (TDS).<br />
A7 Voltage Transformer Capacitive type 230 kV, complete 18 sets<br />
with the required accessories and support structure in<br />
accordance to the requirements of the Technical Data<br />
Sheet (TDS).<br />
A8 Voltage Transformer 69 kV, complete with the required 30 sets<br />
accessories in accordance to the requirements of the<br />
Technical Data Sheet (TDS).<br />
A9 Surge Arresters 192 kV, station type, complete with 12 sets<br />
support structure and the required accessories in<br />
accordance to the requirements of the Technical Data<br />
Sheet (TDS).<br />
Page 2 of 15
DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />
PHASE 3B<br />
ITEM DESCRIPTION<br />
QTY UNIT UNIT COST AMOUNT<br />
A10. Surge Arresters 60 kV, station type, complete with 24 sets<br />
support structure and the required accessories in<br />
accordance to the requirements of the Technical Data<br />
Sheet (TDS).<br />
A11. Substation Gantry and Pedestal Steel Structures 1 lot<br />
including bolts, washer, etc hot dipped galvanized<br />
complete with all the required accessories in accordance<br />
to the requirements of the Technical Data Sheet (TDS)<br />
A12. Metalclad Switchgear, 13.8 kv outdoor type outdoor 2 sets<br />
type complete with arresters, VT, CT, breaker and 150<br />
KVA 13.8/460 vac 3-phase transformer type ONAN<br />
Outdoor type in accordance to the requirements of the<br />
Technical Data Sheet (TDS)<br />
A13 Installation Materials consisting of conductors, 1 lot<br />
insulators, connectors, pole line hardwares, bus<br />
supports, and other accessories in accordance to the<br />
requirements of the Technical Data Sheet (TDS)<br />
A14 Grounding Materials consisting of insulated and bare 1 lot<br />
copper cables, lightning rod, copper rods, fittings.<br />
complete with the required materials for aerial and<br />
grounding mat and to substation equipment and<br />
structures in accordance to the requirements of the<br />
Technical Data Sheet (TDS).<br />
A15. Distribution Board 125 VDC complete with enclosure, 2 sets<br />
main breaker, Automatic transfer switch, tie breaker,<br />
branch breakers, and accessories for installation.<br />
Number of breakers to supply four (4) bays in<br />
accordance to the requirements of the Technical Data<br />
Sheet (TDS)<br />
A16. Station Service Transformer 50 kva 480/230V, three 2 sets<br />
phase, dry type and accessories in accordance to the<br />
requirements of the Technical Data Sheet (TDS).<br />
A17. Distribution Board 3 Phase 460/230 VAC with 2 sets<br />
enclosure, main breaker, tie breaker, automatic transfer<br />
switch, branch circuit and accessories Number of<br />
circuit breaker to include 4 additional bays, breaker to<br />
panel at bay 3 and 4, and spare breaker in accordance to<br />
the requirements of the Technical Data Sheet (TDS)<br />
A18. Distribution Board 3 Phase 230 VAC with enclosure , 2 sets<br />
main breaker, tie breaker, automatic transfer switch,<br />
branch circuit and accessories Number of circuit<br />
breaker for four (4) bays, breaker for panel at bays 3<br />
and 4 and spare breaker in accordance to the<br />
requirements of the Technical Data Sheet (TDS)<br />
A19 Power Control, Instrumentation and Protection 1 lot<br />
Cables, 35kV, 15 kV and 600 volt insulation complete<br />
with insulated terminal lugs, glands, marking etc. in<br />
accordance to the requirements of the Technical Data<br />
Sheet (TDS)<br />
A20. Cable Trays (various type) hot dipped galvanized, 1 lot<br />
complete with supports, fittings, and other accessories in<br />
accordance to the requirements of the Technical Data<br />
Sheet (TDS). Cost of cable tray included at cable<br />
trenches<br />
Page 3 of 15
DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />
PHASE 3B<br />
ITEM DESCRIPTION<br />
QTY UNIT UNIT COST AMOUNT<br />
A21 Switchyard Lighting System (Bay and Perimeter) 1 lot<br />
complete with the required fixtures, posts, conduits,<br />
wires, magnetic contactor and photo cell, conduit<br />
fittings, conductors foundations, etc in accordance to the<br />
requirements of the Technical Data Sheet (TDS)<br />
A22 Substation Control System<br />
a. Microprocessor Based Substation Control System 1 sets<br />
(New back up set ) to include the integration of<br />
new and existing to accommodate all system (six<br />
bays). To include licensed copy of software (latest<br />
Version) and industrial type equipment for the<br />
Protection, control and monitoring of equipment for<br />
connection to SCADA, gateway, HMI and Work<br />
station. To include the integration, data base<br />
reconfiguration, parameterization of the existing<br />
and new MBSC system with BCU, and others to<br />
conform to the new set up of Clark S/S. To provide<br />
CDC with copy of license software in DVD or CD<br />
in accordance to the requirements of the<br />
Technical Data Sheet (TDS).<br />
b. Closed Circuit Television System (New set of<br />
1 sets<br />
CCTV) new system for bays 3,4, 5, 6 and<br />
perimeter fence complete with all the required<br />
peripherals, industrial computer, accessories,<br />
wires and cable reconfiguration and integration<br />
with existing CCTV system. To include the supply<br />
and replacement of existing CCTV controller and<br />
reconfiguration. (No of PTZ dome camera arm<br />
mounted at gantry = six(6), Pole mounted<br />
Motorized pan tilt camera = two(2), CCtv player<br />
recorder controller = (2), Working station with 21<br />
inch Monitor= two (2) and licensed software with<br />
CD or DVD in accordance to the requirements of<br />
the Technical Data Sheet (TDS).<br />
A23<br />
c. Access Control and Alarm Monitoring System<br />
1 lot<br />
(ACAMS) revision / expansion/ integration of<br />
system to include new warehouse and relocation<br />
of existing affected by control building renovation<br />
d. Main Control Switchboard, with all instrument, 1 lot<br />
meters, indicators, control switches, annunciators,<br />
push buttons, LED indicating lamps, terminal<br />
blocks, wiring and miscellaneous auxiliary and<br />
accessory devices<br />
Substation Protection System<br />
a. Transformer Protection ( Main 1) complete with 2 sets<br />
the required protective relays and accessories in<br />
one (1) panel. Different manufacturer from Main 2<br />
in accordance to the requirements of the<br />
Technical Data Sheet (TDS)<br />
b. Transformer Protection ( Main 2) complete with 2 sets<br />
the required protective relays and accessories in<br />
one (1) panel, Different manufacturer from Main 1<br />
in accordance to the requirements of the<br />
Technical Data Sheet (TDS)<br />
Page 4 of 15
DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />
PHASE 3B<br />
ITEM DESCRIPTION<br />
QTY UNIT UNIT COST AMOUNT<br />
c. Breaker Failure Protection System<br />
1 sets<br />
Complete with the required protective relays and<br />
accessories for four (4) 230 kV Power Circuit<br />
Breakers in one panel in accordance to the<br />
requirements of the Technical Data Sheet (TDS).<br />
d. 230 kV Bus Protection System, Main 1 - complete 1 sets<br />
with accessories for connection of new breaker 8-<br />
03CB24CLA and 8-04CB24CLA at Bus 8-<br />
BS03CLA to existing GE B30-8BS03CLA in<br />
accordance to the requirements of the Technical<br />
Data Sheet (TDS)<br />
e. 230 kV Bus Protection System, Main 1 - complete 1 sets<br />
with accessories for connection of new breaker 8-<br />
03CB08CLA and 8-04CB08CLA at Bus 8 -<br />
BS04CLA to existing GE B30-8BS04CLA in<br />
accordance to the requirements of the Technical<br />
Data Sheet (TDS)<br />
d. 230 kV Bus Protection System, (Main 2) complete 2 sets<br />
with the required protective relays and accessories<br />
for the integration of five (5) 230 kV Power Circuit<br />
Breakers (Bus Tie, Bay 3,4,5 and 6 Breakers) in<br />
accordance to the requirements of the Technical<br />
Data Sheet (TDS)<br />
f. 69 kV Feeder Protection System, complete with<br />
the required protective relays and accessories for<br />
the following outgoing 69 kV feeders in<br />
accordance to the requirements of the Technical<br />
Data Sheet (TDS)<br />
f.1 Three (3) 69 kV breakers with two (2) 69 kV 1 sets<br />
outgoing feeders in one (1) panel<br />
f.2 Three (3) 69 kV breakers with two (2) 69 kV 1 sets<br />
outgoing feeders in one (1) panel<br />
g. Bay Control Unit with provision for integration to 2 sets<br />
existing and new Microprocessor Based<br />
Substation Control system complete with<br />
necessary accessories in accordance to the<br />
requirements of the Technical Data Sheet (TDS)<br />
Bay 83 and Bay 84 at Clark 230 kV S/S<br />
A24 Line Protection System<br />
a. Line Protection for 230 kV system (Main 1 -<br />
2 sets<br />
Distance Relay) complete with the required<br />
protective relays and accessories in accordance to<br />
the requirements of the Technical Data Sheet<br />
(TDS).<br />
b. Line Protection for 230 kV system (Main 2 - Line 2 sets<br />
Differential Relay) complete with the required<br />
protective relays and accessories in accordance to<br />
the requirements of the Technical Data Sheet<br />
(TDS).<br />
A25 Capacitive Voltage Transformer 230 kV, complete with 6 units<br />
the required accessories and support structure in<br />
accordance to the requirements of the Technical Data<br />
Sheet (TDS).<br />
Page 5 of 15
DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />
PHASE 3B<br />
ITEM DESCRIPTION<br />
QTY UNIT UNIT COST AMOUNT<br />
A26 Surge Arresters 192 kV, station type, complete with 6 units<br />
support structure and the required accessories in<br />
accordance to the requirements of the Technical Data<br />
Sheet (TDS).<br />
A27 Ganged Disconnect Switch 230kV, 3-phase, 2000A, 2 units<br />
40KA equipped with 460 vac 3 phase motor and<br />
manually group operated, complete with the required<br />
accessories in accordance to the requirements of the<br />
Technical Data Sheet (TDS).<br />
A28 Ganged Disconnect Switch 69kV, 3-phase, 2000A, 38 2 units<br />
kA equipped with 230 vac motor and manually group<br />
operated, complete with the required accessories in<br />
accordance to the requirements of the Technical Data<br />
A29 Ganged Disconnect Switch 69kV, 3-phase, 2000A, 38 2 units<br />
kA equipped with earthing blades, motor and manually<br />
group operated, complete with the required accessories<br />
in accordance to the requirements of the Technical Data<br />
Sheet (TDS)<br />
A30 Voltage Transformer 69 kV, complete with the required 12 units<br />
accessories in accordance to the requirements of the<br />
Technical Data Sheet (TDS)<br />
A31 BATTERY 125 VDC POWER SUPPLY SYSTEM 800 2 units<br />
amp-hour capacity indoor type complete with the<br />
required rack and accessories in accordance with the<br />
requirements of Technical Data Sheet (TDS)<br />
A32 Battery Charger 460 vac 3 phase in accordance with the 2 units<br />
requirements of the Technical Data Sheet (TDS).<br />
A33 Supply and Installation of Emergency Generators with 1 unit<br />
a capacity of 225 KVA, 460/230 vac, 60 HZ with diesel<br />
engine, Day Tank and four (4) 400 amps 480 vac 3-<br />
phase 4 poles ATS<br />
A32 NETWORK DISTURBANCE MONITORING<br />
1 lot<br />
EQUIPMENT (NDME)<br />
Supply of Data acquisition units complete with required<br />
peripherals and accessories. Reconfiguration of existing<br />
NDME to conform with the new set-up/configuration<br />
under this project to include Bay 81, 82, 83, 84, 85 & 86.<br />
The units should be the same brand or latest model and<br />
compatible with the existing unit at the control room.<br />
A33 FIBER OPTIC COMMUNICATION SYSTEM<br />
a. Fiber Optic Terminal Equipment complete with<br />
1 lot<br />
Optical Distribution Frame (ODF), access<br />
multiplexers, circuit protections, indicators,<br />
annunciators, appurtenances, pigtails, patch<br />
cords, complete with the required accessories.<br />
b. Fiber Optic Approach Cable, 36 fibers, 1550 nm, 1 lot<br />
Signal Mode (from station gantry to the Optical<br />
Distribution Frame at the FOT Equipment Room).<br />
Page 6 of 15
DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />
PHASE 3B<br />
ITEM DESCRIPTION<br />
QTY UNIT UNIT COST AMOUNT<br />
c. Protection Signaling Equipment complete with all 2 lot<br />
the necessary interface cables, software and<br />
manuals. Programmable teleprotection unit for<br />
transmitting / receiving minimum of four (4)<br />
independent command signals capable of<br />
communicating over analog and digital<br />
communication channel i.e., MUX (4WE&M,<br />
RS232, V.32, X.21, etc), PLC, copper wire and<br />
fiber optic.<br />
A34<br />
MICROWAVE RADIO COMMUNICATION SYSTEM<br />
a. Digital Microwave Radio Terminal, 16E1, 7GHz, 1+1<br />
MHSB including all necessary accessories i.e. mounting<br />
cabinet, rack/shelf assembly, order wire, fuse and alarm<br />
panel, power supply and jack field (for 16 tributaries)<br />
a.1 Clark S/S<br />
1 lot<br />
a.2 Mexico S/S<br />
1 lot<br />
b. Multiplex Equipment / Channel Bank and associated<br />
cards including all necessary peripheral equipment and<br />
installation accessories i.e. rack/shelf assembly, VF jack<br />
field, MDF, interface and data cable<br />
b.1 Clark S/S<br />
1 lot<br />
b.2 Mexico S/S<br />
1 lot<br />
c. Antenna System and Waveguides including all<br />
installation accessories and peripheral equipment i.e.<br />
antenna mount and support pipe, strut hardware kit,<br />
waveguide support hardware, flanging tools, waveguide<br />
connector etc.<br />
c.1 Clark S/S<br />
1 lot<br />
c.2 Mexico S/S<br />
1 lot<br />
d. Network Management System including all the<br />
necessary hardware and software modules for<br />
management of node element / sub network, i.e.<br />
industrial portable PC with licensed Windows Operating<br />
System and pre installed Network Management software.<br />
d.1 Clark - Mexico MW Radio link<br />
1 lot<br />
e. Protection Signaling Equipment complete with all the 2 lot<br />
necessary interface cables, software and manuals.<br />
Programmable teleprotection unit for transmitting /<br />
receiving minimum of four (4) independent command<br />
signals capable of communicating over analog and digital<br />
communication channel i.e., MUX (4WE&M, RS232,<br />
V.32, X.21, etc), PLC, copper wire and fiber optic.<br />
A35<br />
Spares, Spare parts and tools( see list as per TDS)<br />
a. Power Transformer 1 lot<br />
b. Power Circuit Breaker 230 kV and 69 kV 1 lot<br />
c. 230 kV and 69kV Ganged Disconnect Switches 1 lot<br />
d. 230 Kava and 69 kV Voltage Transformers 1 lot<br />
e. 230 kV and 69 kV Surge Arresters 1 lot<br />
f. Metal clad Switchgear 13.8 kV 1 lot<br />
g. Station Service Transformer 1 lot<br />
h. AC DC aux switchboard 1 lot<br />
Page 7 of 15
DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />
PHASE 3B<br />
ITEM DESCRIPTION<br />
QTY UNIT UNIT COST AMOUNT<br />
i. Storage Batteries 1 lot<br />
j. Battery Charger 1 lot<br />
k. MBSC 1 lot<br />
l. CCTV 1 lot<br />
m. Substation Protection System 1 lot<br />
n. Line Protection System 1 lot<br />
o. Network Disturbance Monitoring 1 lot<br />
p. Fibre Optical Terminal Equipment 1 lot<br />
q. Protection Signaling Equipment 1 lot<br />
r Microwave Radio Telephone equipment 1 lot<br />
Clark Load End Substation at PSPC<br />
A36 Station Service Transformer 75 kva 22.9/0.23kV, three 2 lot<br />
phase, Outdoor ONAN type, 35 kV xlpe cable, 300:5<br />
amp 22.9 kV CT, and accessories in accordance to the<br />
requirements of the Technical Data Sheet (TDS). To<br />
includes bus bar modification, current transformer, cover,<br />
support and wiring/termination to substation protection<br />
system. The scope covers the construction of<br />
foundation, HV and LV wiring and installation of new<br />
transformer.<br />
A37 Distribution Board 3 Phase 230 VAC with enclosure , 2 sets<br />
main breaker, tie breaker, automatic transfer switch, four<br />
(4) 3 poles branch circuit breakers, assorted copper<br />
wires, conduits and accessories in accordance to the<br />
requirements of the Technical Data Sheet (TDS). The<br />
scope includes the wiring and termination to existing<br />
MTS/AC panel and fire suppression panel.<br />
SUB-TOTAL FOR ITEM 3A ELECTRICAL WORKS<br />
B CIVIL WORKS<br />
FURNISH, INSTALL, CONSTRUCT, PLACE, APPLY<br />
AND / OR LAY, INCLUDING FURNISHING <strong>OF</strong> PLANT,<br />
LABOR, EQUIPMENT AND MATERIALS<br />
B1 EQUIPMENT FOUNDATION Consisting of concrete<br />
(211kg/cm²), Non-shirk Grout, Reinforcing Steel Bars<br />
(Grade 275), Excavation and backfill, Leveling Concrete<br />
(141 kg/cm²) and other incidentals required to complete<br />
the works.<br />
a. Power Transformer 2 lot<br />
b. Power Circuit Breaker 12 lot<br />
c. Current Transformer 72 lot<br />
d. Voltage Transformer 12 lot<br />
e. Surge Arresters 24 lot<br />
f. Ganged Disconnect Switch 24 lot<br />
G. Bus Supports 48 lot<br />
f. Emergency Generator set 1 lot<br />
B2 230 kV Gantry Structure Foundation Consisting of<br />
concrete (211kg/cm²), Non-shirk Grout, Reinforcing Steel<br />
Bars (Grade 275), Excavation and backfill, Leveling<br />
Concrete (141 kg/cm²) and other incidentals required to<br />
complete the works.<br />
1 lot<br />
Page 8 of 15
DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />
PHASE 3B<br />
ITEM DESCRIPTION<br />
QTY UNIT UNIT COST AMOUNT<br />
B3 Roadways, Parking Area, Concrete Curve & Gutter, 2227 sq.m<br />
Open stock yard Construction of access road from the<br />
existing roadway to the transformer area and parking<br />
area at warehouse, consisting of Concrete Pavement<br />
(246kg/cm²), Curb and Gutter (211kg/cm²) including<br />
dowels, Reinforcing steel bars (Grade 275), Aggregate<br />
Sub-Base and other incidentals to complete the work.<br />
B4 Drainage System - Consisting of different sizes of 435 lm<br />
RCDP, Drainage Appurtenances consisting of Concrete (Main)<br />
(211kg/cm²), Reinforcing steel bars Grade 275,<br />
Excavation and backfill, Miscellaneous Steel (ASTM 300 lm<br />
A36), CHB including demolition/restoration works for the (Sec.)<br />
affected portion of the existing drainage appurtenances<br />
and other incidentals to complete the work.<br />
B5 Oil/Water Separator - Consisting of concrete 1 lot<br />
(211kg/cm²), Reinforcing Steel Bars (Grade 275),<br />
Excavation and backfill, Miscellaneous Steel, Galvanized<br />
Steel pipe, B.I. Pipe, including its tapping to the nearest<br />
drainage system and other incidentals required to<br />
complete the work.<br />
B6 Concrete Firewall - Between transformers consisting of 1 lot<br />
Concrete (211kg/cm²), Reinforcing Steel Bars (Grade<br />
275), Excavation and Backfill, Leveling Concrete<br />
(141kg/cm²) and other incidentals required to complete<br />
the work.<br />
B7 Cable Trenches - Consisting of Concrete (211kg/cm²) 400 l.m.<br />
Reinforcing Steel Bars (Grade 275), Excavation, leveling (Main)<br />
Concrete (141kg/cm²), Checkered Steel Plate Cover,<br />
Stiffener, Embedded Metals, Steel angle, galvanized<br />
cable tray, pits, Discharge Pipes including 200 l.m.<br />
demolition/restoration works for the affected portion of (Branches)<br />
the existing cable trench to connect the new cable trench<br />
and other incidentals to complete the work.<br />
B8 Cable Pipe Crossing Roadways - Consisting of 12 l.m.<br />
concrete (211kg/cm²), Reinforcing Steel Bars (Grade<br />
275) Excavation, Sand and Gravel bedding, uPCV Pipes,<br />
Discharge Pipes and other incidentals required to<br />
complete the works.<br />
B9 Switchyard Gravel Surfacing - Gravel surfacing on the 1200 cu.m<br />
bays where the equipment will be installed with the lines<br />
and extent as directed by the owner.<br />
B10 Seclusion Fence and Gate - Enclosing the 230kV and 235 l.m.<br />
69kV switchyard consisting of Hot Dipped Galvanized<br />
Wire Mesh Gauge #10, G.I. Pipes Schedule 40,<br />
Miscellaneous Steel (ASTM A36), Concrete (211 kg/cm²)<br />
Reinforcing Steel Bars (Grade 275), Excavation and<br />
Backfill, and other incidentals to complete the work.<br />
B11 Embankment of Substation Expansion Area -<br />
7040 sq.m.<br />
Consisting of clearing, grading, and embankment with<br />
compaction in layers to match the existing finish grade in<br />
accordance with DPWH Standard Specifications.<br />
Page 9 of 15
DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />
PHASE 3B<br />
ITEM DESCRIPTION<br />
QTY UNIT UNIT COST AMOUNT<br />
B12 Retaining Wall and Perimeter Fence of Substation 295 l.m.<br />
Expansion Area - Consisting of Concrete (211kg/cm²),<br />
Reinforcing steel bars Grade 275, Excavation and<br />
backfill, CHB including demolition/restoration works for<br />
the affected portion of the existing retaining<br />
wall/perimeter fence and other incidentals to complete<br />
the work. To include painting of walls and perimeter<br />
fence and affected areas.<br />
B13 69kV Gantry Structure Foundation Consisting of 1 set<br />
concrete (211kg/cm²), Non-shirk Grout, Reinforcing Steel<br />
Bars (Grade 275), Excavation and backfill, Leveling<br />
Concrete (141 kg/cm²) and other incidentals required to<br />
complete the works.<br />
B14 Expansion of Existing Clark 230KV S/S Control 115 sq.m.<br />
House Consisting of architectural, civil, electrical,<br />
mechanical, and finishing works to match the existing. To<br />
include supply of 3-3 tons split air conditioning units,<br />
industrial type exhaust fan, fire detection units to connect<br />
to existing Fire Alarm panel, lights and outlets, wiring and<br />
other accessories and incidentals to complete the work.<br />
To include repainting of Bldg external and affected<br />
areas.<br />
B15 Proposed Clark 230KV S/S Warehouse Consisting of 288 sq.m.<br />
architectural, civil/structural, electrical, and mechanical<br />
works for the construction of steel frame warehouse with<br />
minimum beam height of 6.00 meters. To include supply<br />
and installation of industrial exhaust fans, lighting fixtures<br />
and outlets. Painting of building internal and external.<br />
B16 Fire Water System,<br />
a. Cleaning & Flushing of following existing facilities<br />
1. 100 mm 440 mtrs<br />
2. 50 mm 110 mtrs<br />
3. 40 mm 200 mtrs<br />
4. Assorted sizes to control room, guard house 100 mtrs<br />
and green area<br />
5. Elevated Water Tank 10,000 gal<br />
1 set<br />
b. New Installation of the following<br />
1. 100 mm GI super sched 40 underground line 420 mtrs<br />
2.<br />
with fittings, valves sand beddings and with<br />
protection membrane<br />
Fire hose reel cabinet with 40 mm brass 12 sets<br />
nozzle, 40 mm x 30 mtrs hose, 40 mm brass<br />
valve, fittings, glass, painted gauge #10 metal<br />
sheet and concrete foundation.<br />
3. Road Crossing of Fire water line, include 9 mtrs<br />
cutting, excavation, backfilling, sand bedding<br />
and road concreting<br />
B17 Rehabilitation of Existing Water Well, includes<br />
100 mtrs<br />
suctioning/cleaning of existing water well including use of<br />
equipment (air compressor and other cleaning equipment)<br />
B18 Replacement of Existing Submersible Pump multistage<br />
type, 100 GPM, 95 meters TDH complete with control and<br />
including Pull out of existing and installation of new<br />
submersible pump.<br />
1 unit<br />
Page 10 of 15
DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />
PHASE 3B<br />
ITEM DESCRIPTION<br />
QTY UNIT UNIT COST AMOUNT<br />
B19 Rehabilitation of Existing Fire Pump, includes<br />
1 unit<br />
cleaning of pumps, testing, electrical system and ready<br />
for operation.<br />
B20 Rehabilitation of Existing Jockey Pump, includes 1 unit<br />
cleaning of pumps, testing, electrical system and ready<br />
for operation.<br />
B21 Brand New Truck Loader Cargo Crane 1 unit<br />
Gross vehicle mass including crane 8,000, Crane<br />
capacity 5,000 kg at 2.4 meters, Maximum lift above<br />
ground 10 Meters, With Hydraulic motors for winch, and<br />
swing, Hydraulic extended Outriggers, Hydraulic pump,<br />
and powered thru PTO. For turn over to CDC-ECMD<br />
SUB-TOTAL FOR ITEM 3B CIVIL WORKS<br />
TOTAL CLARK SUBSTATION 230/69KV<br />
4.0 Metering System (230kV System) 6 sets<br />
Current transformer Multi ratio 2000:5A 0.3 accuracy<br />
class, Burden B-0.1 to 0.9, Voltage transformer 0.3<br />
accuracy, weather proof enclosure for Billing meter for<br />
the electronic billing system in accordance to the<br />
requirements and specification of the power provider<br />
(NGCP/TRANSCO) for T1, T2, T3, T4, T5 and T6.<br />
5.0 GRID IMPACT STUDY, including request and payment 1 lot<br />
for the data, review and approval of NGCP<br />
6.0 OCCUPATIONAL HEALTH AND SAFETY 1 lot<br />
includes personal protective equipment, clinical<br />
materials, signage's and barricades, and the salary and<br />
wages of health and safety personnel.<br />
7.0<br />
Facilities For The Engineer such as temporary field<br />
office, including all necessary electricity, water,<br />
telephone services, office equipment, furniture and<br />
the following for the use of CDC/ECMD Engineers.<br />
For turn over to CDC-ECMD after the completion of<br />
the project<br />
a Field Office (20 ft Container with AC unit)<br />
2 units<br />
b Laptops Intel Core i7-2410 processor, Window 7 4 units<br />
c<br />
pro, MS Office 2007 with external 1TB hard Drive<br />
Desktop Intel i7-550 Processor, Window 7 pro, MS 2 units<br />
office 2007 with external 1TB hard drive<br />
d Licensed AUTOCAD (2010 or latest) softwares 2 units<br />
e Licensed Ms Project (2010 or latest) softwares 2 units<br />
f Service Vehicle Twin Cab Pick up 4 x 4 (3.0 diesel 2 units<br />
engine, common rail direct injection) with fuel,<br />
driver, maintenance, other costs (Toll fee, parking)<br />
for 14 months (lease to own)<br />
g Service Vehicle AUV 4 x 2 (2.5 Diesel engine) with 1 unit<br />
fuel, driver and maintenance, others (Toll, parking<br />
fee) costs for 14 months (lease to own)<br />
Page 11 of 15
DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />
PHASE 3B<br />
ITEM DESCRIPTION<br />
QTY UNIT UNIT COST AMOUNT<br />
h Digital SLR Camera 15 megapixel with zoom 105, 2 units<br />
extra 8GB memory card and bag.<br />
i Flat bed scanner A4<br />
1 unit<br />
j Color Printer A3 paper size complete with supply 1 unit<br />
of paper and ink for the duration of the project<br />
k Professional Infrared Thermal Imagers<br />
1 unit<br />
l Voice recorder 8GB, Built-in Li-Ion Battery<br />
1 unit<br />
8.0<br />
A<br />
MEXICO 230 KV SUBSTATION Bay 87 and 88<br />
(All in accordance with NGCP specifications)<br />
ELECTRICAL WORKS<br />
Supply, manufacture, factory testing, and furnishing of<br />
labor, equipment, tools and incidental materials for the<br />
delivery, assembly, erection, installation, field testing<br />
commissioning and ready for operation of the following<br />
substation equipment and its associated control and<br />
protection system and accessories<br />
A1 Power Circuit Breaker Live Tank 230kV, 3-phase, 2 sets<br />
3000A, 40, kA single and three pole operation (3+1),<br />
complete with the required accessories and support<br />
structure<br />
A2 Ganged Disconnect Switch 230kV, 3-phase, 3000A, 2 sets<br />
44KA equipped with 460 vac 3 phase motor and<br />
manually group operated, complete with the required<br />
accessories<br />
A3 Ganged Disconnect Switch 230kV, 3-phase, 3000A, 2 sets<br />
44KA equipped with earthing, 460 vac 3 phase motor<br />
and manually group operated, complete with the required<br />
accessories<br />
A4 Capacitor Voltage Transformer (CVT) 230 kV, 3 sets<br />
complete with the required accessories and support<br />
structure.<br />
A5 Surge Arresters 192 kV, station type, complete with 3 sets<br />
support structure and the required accessories<br />
A6 Substation Gantry and Pedestal Steel Structures 1 lot<br />
including bolts, washer, etc hot dipped galvanized<br />
complete with all the required accessories<br />
A7 Installation Materials consisting of conductors, 1 lot<br />
insulators, connectors, pole line hardwares and other<br />
accessories<br />
A8 Grounding Materials consisting of insulated and bare 1 lot<br />
copper cables, lightning rod, copper rods, fittings.<br />
complete with the required materials for aerial and<br />
grounding mat and to substation equipment and<br />
structures.<br />
A9 AC and DC Auxiliary Panels Indoor type, complete with 1 lot<br />
the required equipment, devices and required<br />
accessories<br />
Page 12 of 15
DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />
PHASE 3B<br />
ITEM DESCRIPTION<br />
QTY UNIT UNIT COST AMOUNT<br />
A10 Distribution Board 125 VDC complete with enclosure, 1 lot<br />
main, Automatic transfer switch, tie breaker, branch<br />
breakers, and accessories for installation.<br />
A11 Distribution Board 3 Phase 230 VAC with enclosure , 1 lot<br />
main breaker, tie breaker, automatic transfer switch,<br />
branch circuit and accessories<br />
A12 Cable Trays (various type) hot dipped galvanized,<br />
1 lot<br />
complete with supports, fittings, and other accessories.<br />
Cost of cable tray to be included at cable trenches<br />
A13<br />
Substation Control System<br />
Main Control Switchboard, with all instrument, meters,<br />
indicators, control switches, annunciators, push buttons,<br />
LED indicating lamps, terminal blocks, wiring and<br />
miscellaneous auxiliary and accessory devices<br />
1 lot<br />
Bay Control Unit with provision for integration to existing<br />
Micro Processor Base Control System complete with<br />
necessary accessories<br />
1 lot<br />
A14<br />
Substation Protection System<br />
a. Breaker Failure Protection System Complete with 1 set<br />
the required protective relays and accessories for<br />
four (4) 230 kV Power Circuit Breakers in one<br />
panel.<br />
b. 230 kV Bus Protection System, - complete with the 1 lot<br />
required Peripheral Unit protective relays and<br />
accessories for the integration of two (2) 230 kV<br />
Power Circuit Breakers<br />
A15<br />
Line Protection System<br />
a. Distance Protection System (Main 1 and Main 2 sets<br />
2) Main 1 complete with the required protective<br />
relays and accessories in one panel and Main 2<br />
complete with the required protective relays and<br />
accessories in one panel.<br />
b. Differential Protection System (Main 1 and Main 2 sets<br />
2) Main 1 complete with the required protective<br />
relays and accessories in one panel and Main 2<br />
complete with the required protective relays and<br />
accessories in one panel.<br />
A16 Current Transformers 230 kV, Multi-ratio, three core, 12 sets<br />
outdoor type oil filled, free standing complete with<br />
support structure and required accessories in<br />
accordance with NGCP specs.<br />
A17 Power Control , Instrumentation and Protection<br />
1 lot<br />
Cables, complete with insulated terminal lugs, glands,<br />
etc.<br />
Page 13 of 15
DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />
PHASE 3B<br />
ITEM DESCRIPTION<br />
QTY UNIT UNIT COST AMOUNT<br />
A18 Fiber Optic Communication System<br />
a. Fiber Optic Terminal Equipment complete with 1 lot<br />
Optical Distribution Frame (ODF), access<br />
multiplexers, circuit protections, indicators,<br />
annunciators, appurtenances, pigtails, patch<br />
cords, complete with the required accessories.<br />
b. Fiber Optic Approach Cable, 36 fibers, 1550nm, 1 lot<br />
signal mode (from station gantry to the Optical<br />
Distribution Frame at the FOT Equipment Room.<br />
c. Protection Signaling Equipment complete with all 1 lot<br />
the necessary interface cables, software and<br />
manuals. Programmable teleprotection unit for<br />
transmitting / receiving minimum of four (4)<br />
independent command signals capable of<br />
communicating over analog and digital<br />
communication channel i.e., MUX (4WE&M,<br />
RS232, V.32, X.21, etc), PLC, copper wire and<br />
fiber optic.<br />
A19<br />
Microwave Radio Communication System<br />
a. Complete integration and interconnection of<br />
1 lot<br />
existing FOT and MW telecommunication system<br />
with associated equipment including interface<br />
cables, MUX equipment / channel cards, etc.<br />
b. Protection Signaling Equipment complete with all 1 lot<br />
the necessary interface cables, software and<br />
manuals. Programmable teleprotection unit for<br />
transmitting / receiving minimum of four (4)<br />
independent command signals capable of<br />
communicating over analog and digital<br />
communication channel i.e., MUX (4WE&M,<br />
RS232, V.32, X.21, etc), PLC, copper wire and<br />
fiber optic.<br />
A20 NETWORK DISTURBANCE MONITORING<br />
1 Lot<br />
EQUIPMENT Supply of DAU complete with cables and<br />
accessories, Reconfiguration of the existing NDME to<br />
conform with the new setup/configuration of the<br />
substation under this project<br />
A21 Spares, Spare parts and tools:<br />
a. 230 kV Power Circuit Breakers<br />
1 lot<br />
b. 230 kV Ganged Disconnect Switches<br />
1 lot<br />
c. 230 kV Coupling Capacitor Voltage Transformers<br />
1 lot<br />
d. 230 kV Surge Arresters<br />
1 lot<br />
e. 230 kV Current Transformers<br />
1 lot<br />
f. Substation and Line Protection System (incl at Clark SS) 1 lot<br />
g. 460,230 VAC & 125 VDC Auxiliary Switchboard<br />
1 lot<br />
SUB-TOTAL FOR ITEMS 8A ELECTRICAL WORKS<br />
B CIVIL and ARCHITECTURAL WORKS<br />
Complete Design, Furnish, install, construct, place, apply<br />
and/or lay, including furnishing of plant, labor, equipment<br />
and materials<br />
Page 14 of 15
DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT -<br />
PHASE 3B<br />
ITEM DESCRIPTION<br />
QTY UNIT UNIT COST AMOUNT<br />
B1<br />
Equipment Foundation consisting of concrete (211<br />
kg/sq. cm, NGCP specs), Non-shirk Grout, Reinforcing<br />
steel Bars (Grade 275, NGCP specs), Excavation and<br />
backfill, Leveling Concrete (141 kg/sq. cm) and other<br />
incidentals required to complete the works.<br />
a. Power Circuit Breakers<br />
6 lot<br />
b. Ganged Disconnect Switches<br />
12 lot<br />
c. Capacitor Voltage Transformers<br />
3 lot<br />
d. Surge Arresters<br />
3 lot<br />
e. Current Transformers<br />
12 lot<br />
B2 230 kV Gantry Structure Foundation Consisting of<br />
1 lot<br />
concrete (211kg/sq cm), Non-shrink Grout, Reinforcing<br />
Steel Bars (Grade 275), Excavation and backfill, Leveling<br />
Concrete (141) kg/sq cm) and other incidentals required<br />
to complete the works.<br />
B3 Roadways, Concrete Curve & Gutter Construction of 1 lot<br />
access road from the existing roadway to the switchyard<br />
area, consisting of concrete pavement (246 kg/ sq cm),<br />
curb and gutter (211 kg/ sq cm) including dowels,<br />
Reinforcing Steel bars (Grade 275, Aggregate sub-base<br />
and other incidentals required to complete the work.<br />
B4 Drainage System, Consisting of different sizes of RCDP, 1 lot<br />
drainage appurtenances consisting of concrete (211kg/<br />
sq cm), Reinforcing steel bars Grade 275, Excavation<br />
and backfill, miscellaneous Steel (ASTM A36), CHB<br />
including demolition/restoration works for the affected<br />
portion of the existing drainage appurtenances and other<br />
incidentals required to complete the works.<br />
B5 Cable Trenches Consisting of concrete (211 kg/sq cm) 50 l.m.<br />
Reinforcing Steel Bars Grade 275, Excavation, leveling<br />
concrete (141 kg/sq cm), checkered steel plate cover,<br />
stiffener, embedded metals, steel angle, pits, discharge<br />
pipes including demolition/restoration and works for the<br />
affected portion of the existing cable trench to connect<br />
the new trench and other incidentals required to<br />
complete the works.<br />
B7 Switchyard Gravel Surfacing, Gravel surfacing on the 1 lot<br />
bays where the equipment will be installed with lines and<br />
extent as directed by the owner.<br />
SUB-TOTAL FOR ITEM 8B CIVIL WORKS<br />
9.0 Reconfiguration/ Parameterization/ Data Base<br />
1 lot<br />
Configuration of existing MBSC System complete with<br />
Bay Control units, Cables, accessories, peripheral, etc.<br />
to conform with the new set-up of NGCP Mexico<br />
Substation<br />
TOTAL MEXICO SUBSTATION 230KV<br />
TOTAL PROJECT DIRECT COST<br />
Page 15 of 15