CITY OF DELAWARE 2009-2013 CAPITAL IMPROVEMENT PROGRAM Project: Justice Center HVAC Overhaul Description and Purpose: Aging heat pump replacement program for Justice Center – 70 N. Union Street Department: Public Works – Building Maintenance Division Fund: Capital Improvement Fund (Fund 410) Justification: The Justice Center currently has 43 heat pumps that are 15 years old. The average operation expectation for these units is 12-15 years. The proposed 5 year plan would replace approximately 9 units per year. Recommended Funding: R E C O M M E N DE D F U N D IN G E s t i m a t e d E x p e nd it ur e s 20 09 20 10 2 01 1 2 01 2 20 13 T o ta ls H V A C R e p lac e m en t $ 2 3 ,1 0 0 $ 2 3 ,8 0 0 $ 2 4 ,5 0 0 $ 2 5 ,2 0 0 $ 9 6 ,6 0 0 T o ta ls $ 2 3 ,1 0 0 $ 2 3 ,8 0 0 $ 2 4 ,5 0 0 $ 2 5 ,2 0 0 $ 9 6 ,6 0 0 So ur ce o f F un d s 20 09 20 10 2 01 1 2 01 2 20 13 T o ta ls G e n e ra l F u n d $ 2 3 ,1 0 0 $ 2 3 ,8 0 0 $ 2 4 ,5 0 0 $ 2 5 ,2 0 0 $ 9 6 ,6 0 0 T o ta ls $ 2 3 ,1 0 0 $ 2 3 ,8 0 0 $ 2 4 ,5 0 0 $ 2 5 ,2 0 0 $ 9 6 ,6 0 0 84

CITY OF DELAWARE 2009-2013 CAPITAL IMPROVEMENT PROGRAM Project: Justice Center Boiler Replacement Description and Purpose: Aging heating system boilers replacement program for Justice Center – 70 N. Union Street Department: Public Works – Building Maintenance Division Fund: Capital Improvement Fund (Fund 410) Justification: The Justice Center currently has 3 boilers that are 16 years old. The average operation expectation for these units is 12-15 years. The proposed 5 year plan would replace approximately 2 units over the next three years. One boiler was replaced during the recent renovations however another unit is inoperable. Recommended Funding: R E C O M M E N DE D F U N D IN G E s t i m a t e d E x p e nd it ur e s 20 09 20 10 2 01 1 2 01 2 20 13 T o ta ls H e a t Sy ste m B oiler $ 2 8 ,0 0 0 $ 0 $ 3 0 ,0 0 0 $ 0 $ 0 $ 5 8 ,0 0 0 T o ta ls $ 2 8 ,0 0 0 $ 0 $ 3 0 ,0 0 0 $ 0 $ 5 8 ,0 0 0 So ur ce o f F un d s 20 09 20 10 2 01 1 2 01 2 20 13 T o ta ls G e n e ra l F u n d $ 2 8 ,0 0 0 $ 0 $ 3 0 ,0 0 0 $ 0 $ 0 $ 5 8 ,0 0 0 T o ta ls $ 2 8 ,0 0 0 $ 0 $ 3 0 ,0 0 0 $ 0 $ 5 8 ,0 0 0 85

CITY OF DELAWARE<br />

2009-2013 CAPITAL IMPROVEMENT PROGRAM<br />

Project: Justice Center HVAC Overhaul<br />

Description and Purpose:<br />

Aging heat pump replacement program for Justice Center – 70 N. Union Street<br />

Department:<br />

Public Works – Building Maintenance Division<br />

Fund:<br />

<strong>Capital</strong> <strong>Improvement</strong> Fund (Fund 410)<br />

Justification:<br />

The Justice Center currently has 43 heat pumps that are 15 years old. The<br />

average operation expectation for these units is 12-15 years. The proposed 5<br />

year plan would replace approximately 9 units per year.<br />

Recommended Funding:<br />

R E C O M M E N DE D F U N D IN G<br />

E s t i m a t e d E x p e nd it ur e s 20 09 20 10 2 01 1 2 01 2 20 13 T o ta ls<br />

H V A C R e p lac e m en t $ 2 3 ,1 0 0 $ 2 3 ,8 0 0 $ 2 4 ,5 0 0 $ 2 5 ,2 0 0 $ 9 6 ,6 0 0<br />

T o ta ls $ 2 3 ,1 0 0 $ 2 3 ,8 0 0 $ 2 4 ,5 0 0 $ 2 5 ,2 0 0 $ 9 6 ,6 0 0<br />

So ur ce o f F un d s 20 09 20 10 2 01 1 2 01 2 20 13 T o ta ls<br />

G e n e ra l F u n d $ 2 3 ,1 0 0 $ 2 3 ,8 0 0 $ 2 4 ,5 0 0 $ 2 5 ,2 0 0 $ 9 6 ,6 0 0<br />

T o ta ls $ 2 3 ,1 0 0 $ 2 3 ,8 0 0 $ 2 4 ,5 0 0 $ 2 5 ,2 0 0 $ 9 6 ,6 0 0<br />

84