Sr. No Activity Risk <strong>Audit</strong> Steps<br />

evaluating project progress<br />

G<br />

Post Construction activities<br />

20 Completion Certificates • Non availability of project completion<br />

certificates<br />

• Payment processed without completion<br />

of project mile stones<br />

• Obtain the completion certificates for the completed Projects<br />

• Obtain the approved Plan for the Project<br />

• Verify whether completion certificates along with backup documentation<br />

evidencing completion, are available for each completed work<br />

• Compare the actual date of completion as per the completion<br />

certificates against the planned completion date as per the approved<br />

Project Plan<br />

• Verify whether the reasons for delay in Project completion are analyzed<br />

by the department<br />

• Verify whether there is a clear demarcation between delay attributable<br />

to Internal factors and delay attributable to the Contractor/ Vendor<br />

• Verify whether where the delays are caused by the service providers,<br />

whether appropriate amount of liquidated damages have been levied in<br />

accordance with the contract terms<br />

• Verify whether the final payment is processed only after ensuring that all<br />

deliverables have been met and completion certificates are in place for<br />