Government of <strong>Uttarakhand</strong><br />

<strong>Audit</strong> <strong>Manual</strong><br />

Sr. No Activity Risk <strong>Audit</strong> Steps<br />

D<br />

Construction Stage<br />

11 Commencement of Work<br />

(Refer Para 375 of Volume VI of<br />

Financial Handbook)<br />

• Commencement of work without<br />

obtaining administrative, financial and<br />

technical approvals<br />

• Check that no work commences unless a properly detailed design and<br />

estimate (technical sanction)has been sanctioned by the competent<br />

authority<br />

• Check that no work commences unless an allotment of funds has been<br />

made and orders for its commencement have been issued by the<br />

competent authority<br />

• Check that, if on grounds of urgency, an officer is required to carry out a<br />

work for which no estimates have been sanctioned, the orders of the<br />

officer authorizing should be available in writing<br />

• Check that the officer required to carry out the work in urgency without<br />

sanctioned estimates had immediately intimated this fact to the<br />

Accountant General and also provided an approximate amount of<br />

liability which he would incur in compliance with the written orders<br />

received<br />

• Check that an engineer in charge is nominated by the competent<br />

authority for the purpose of operating a particular contract and the same<br />

is indicated in the work order/contract<br />

• Verify that work progress – bar chart is prepared for work milestone<br />

Page 354 of 705