Government of <strong>Uttarakhand</strong><br />

<strong>Audit</strong> <strong>Manual</strong><br />

Sr. No Activity Risk <strong>Audit</strong> Steps<br />

for expenditure to be made on preparatory works such as survey,<br />

investigation and engineering etc<br />

• Verify whether the Capital Budget is prepared in detail including<br />

separate heads of land ,building and development cost<br />

• Verify whether revision in budgets have been formally approved as per<br />

authority of approval<br />

10 Project Schedule and Milestone<br />

definition<br />

• Preparation of Project Schedule without<br />

defining timelines for each Milestone<br />

• Verify whether all the projects initiated during the audit period have<br />

been duly approved as per the Delegation of Powers<br />

• Verify whether for all the approved Project Plans, milestones have been<br />

clearly identified and time-lines for completion of each milestone have<br />

been defined<br />

• Verify whether a detailed program with master plan of the work is being<br />

prepared for effective monitoring<br />

• Verify whether the monitoring program is flexible enough<br />

to permit modifications to meet unknown contingencies that disturb the<br />

planned sequence of operations<br />

• Verify whether systematic steps are taken to ensure<br />

the program is closely followed to achieve the desired<br />

level of progress at work<br />

Page 353 of 705