24.03.2015 Views

Audit Manual - Core Treasury System Uttarakhand

Audit Manual - Core Treasury System Uttarakhand

Audit Manual - Core Treasury System Uttarakhand

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Government of <strong>Uttarakhand</strong><br />

<strong>Audit</strong> <strong>Manual</strong><br />

Sr. No Activity Risk <strong>Audit</strong> Steps<br />

Extension in project completion date should have been approved<br />

as per the delegation of power<br />

Where there are delays in the commencement of the Project, have<br />

subsequent activities (such as Procurement of Project material)<br />

been re-scheduled in line with the extension in the Original Project<br />

timelines to avoid Blockage of Working Capital, if any<br />

C<br />

Budgeting, Scheduling and Milestone Definition<br />

9 Budgetary Controls • Inadequate approvals for budgets (Initial<br />

& revised)<br />

• Risk of overspending<br />

• Defalcation and losses<br />

• Verify whether the approved annual budget for the works is available<br />

• Verify whether expenditure for all works<br />

incurred up to the end of the last financial year have been compiled and<br />

incorporated while preparing the budget<br />

• Verify whether a percentage of provision is made in the budget for spill<br />

over works carried forward to the next year<br />

• Verify whether the completion schedule and approximate value<br />

of each contract is mentioned in the budget<br />

• Verify whether a certain percentage of provision is made in the budget<br />