Section 01811<br />

Page 1<br />

SECTION 01811<br />

BUILDING ENVELOPE COMMISSIONING<br />

PART 1<br />

GENERAL<br />

1.1 RELATED DOCUMENTS<br />

A. This section is only a portion of the Contract Documents. All of the Contract Documents,<br />

including Conditions of the Contract and Division 01 General Requirements, apply to this section.<br />

Refer to Divisions 03 through 14 for requirements specific to each Section.<br />

B. Owner’s Project Requirements (OPR) and Basis of Design (BOD) documentation are included<br />

for information only.<br />

1.2 SUMMARY<br />

This Section includes building envelope commissioning procedures, including substructure, superstructure,<br />

exterior enclosure, and roofing construction that protects climate controlled interior space from unconditioned<br />

spaces and the exterior environment.<br />

A. Commissioning<br />

1. A systematic process of ensuring that all building enclosure systems perform interactively<br />

according to the Architect’s BOD and the OPR. This is to be achieved through actual<br />

verification of systems performance during the construction period.<br />

2. The commissioning process does not take away from, or reduce the responsibility of, the<br />

General Contractor and installing subcontractors to provide a finished and fully functioning<br />

product.<br />

3. Whole building commissioning includes both MEP commissioning agents and building<br />

enclosure commissioning agents. This specification only addresses building enclosure<br />

commissioning.<br />

B. Building Envelope/Enclosure Commissioning Service Procurement: The Owner shall or<br />

Mechanical Commissioning Agent shall retain a Building Envelope/Enclosure Commissioning Agent<br />

(BECA) for the Project to provide building enclosure coordination and to oversee the commissioning<br />

of all building enclosure components.<br />

C. Systems to be Commissioned: Sections of Work to be commissioned include, but are not<br />

limited to, the sections of the building that include materials and assemblies that are responsible for<br />

creating environmental separation. All performance values shall be as described within each<br />

individual section.<br />

1.3 COMMISSIONING TEAM MEMBERS<br />

A. Commissioning Team<br />

1. Owner (PM) and his/her consultants<br />

2. General Contractor (GC or Contractor)<br />

3. Designer and design engineers (particularly the Architect and Engineers – A/E)<br />

4. Building Envelope/Enclosure Commissioning Authority (BECA)<br />

5. Specialty subcontractors<br />

6. Building Enclosure Testing Agency (BETA)<br />

1.4 CONTRACTOR'S RESPONSIBILITIES<br />

A. Provide complete set of Coordination Drawings (see 1.9 Building Enclosure Coordination<br />

Drawings) showing the complete coordination and integration of all Work of commissioned systems to<br />

the BECA.<br />

B. Provide cut sheets and shop drawing submittals of commissioned systems to the BECA.<br />

C. Attend pre-construction, design, and construction phase building enclosure coordination<br />

meetings.<br />

D. Provide test data, letters of compatibility, and certificates to BECA.<br />

NAPA CENTURY CENTER XD 12<br />