5. The electrical contractor is to be responsible for employing the proper tradesmen per union<br />

jurisdiction, past, present, and future. The subcontractor is also responsible for taking whatever<br />

measures that may be necessary, including composite crews, to settle any labor disputes and insure<br />

job continuity at no additional cost to the Owner. Should questions of union jurisdiction arise, the<br />

contractor shall immediately take steps to settle such disputes and will use such labor as may be<br />

determined to have jurisdiction at no additional cost to the Owner or General Contractor. Any work<br />

claimed by the Union(s), including terminations of wiring systems for Owner provided equipment,<br />

shall be included by this contractor at no additional cost to the Owner or the General contractor.<br />

Should he fail to take expeditious action, he will be responsible for the time lost and monetary<br />

damages because of delays arising from such disputes.<br />

6. The electrical contractor shall provide a journeyman electrician standing by at the project for<br />

the first three days (and nights) of the project’s opening.<br />

1.08 ALTERNATES<br />

A. The Contractor shall determine the scope of each specified alternate proposal by carefully reading all<br />

Divisions of the Contract Documents. The Bid Form contains information explaining the extent of the<br />

construction to be performed under a specific alternate. Alternate proposals which are not<br />

predominantly electrical in scope, are described in other Divisions of the Contract Documents.<br />

1.09 SUPPORT SYSTEM DESIGN FOR ELECTRICAL SYSTEMS<br />

A. The Division 16 Contractor is responsible for design of all electrical support systems, including<br />

hangers, Unistrut, backing, etc.<br />

1.10 GENERAL REQUIREMENTS FOR ALL MATERIALS<br />

A. Provide all parts and accessories necessary for equipment and complete installation.<br />

B. Provide factory applied finish on all exterior surfaces of electrical equipment. Any item which has the<br />

finish marred shall be refinished to a new condition before final acceptance.<br />

C. Provide three copies of spare parts lists, and operating and maintenance instructions for all<br />

distribution apparatus, major equipment, and auxiliary systems. These shall be bound in folders with<br />

suitable identification on front cover. Deliver to Architect prior to final acceptance.<br />

D. All materials shall be new and of good quality, and shall bear the stamp of approval of the<br />

Underwriters' Laboratories, Inc.<br />

1.11 NOISE<br />

A. Eliminate any abnormal noises, which are not considered by the Architect to be an inherent part of the<br />

systems as designed.<br />

B. Abnormal buzzing in equipment components will not be acceptable.<br />

1.12 SUBSTITUTIONS<br />

A. Substitutions will be considered up to 2 weeks prior to bid. All approvals must be in via email from<br />

spatton@ediengineers.com.<br />

B. The names of manufacturers and model numbers have been used in the Contract Documents to<br />

establish types of equipment and standards of quality.<br />

1. While it is not the intention of the Architect to discriminate against any manufacturer of<br />

equipment which may be equivalent to specified equipment, a strict interpretation of such<br />

equivalency will be exercised in considering any equipment offered as a substitute for<br />

specified equipment. The Contractor shall submit with each request for approval of substitute<br />

material or equipment, sufficient data to show conclusively that it is equivalent to that<br />

specified in the following respects:<br />

a. Performance:<br />

1) Energy consumption at the point of rating shall not exceed that of the<br />

specified equipment.<br />

2) Vibration and noise production at the point of rating shall not exceed that of<br />

the specified equipment.<br />

Cinemark 16000 - 4 General Conditions for Electrical Work<br />

South Napa Century Center XD 12 EnviroDesign, Inc., Bid Issue 7-7-11