Document 00800<br />

Page 6<br />

7.4 In the fist line delete the word “…Architect…” and insert the word “…Owner…” In the third line delete the<br />

word "Architect" and insert the word "Owner".<br />

ARTICLE 8<br />

TIME<br />

8.1.3 After the word “…Architect…’ and insert the words “…and approved by Owner…”<br />

8.3.1 In the fifth line delete the word “…Architect…” and insert the word “…Owner….” In the sixth line delete the<br />

word “…Architect…” and insert the word “…Owner…”<br />

Add the following at the end of Paragraph 8.3.1:<br />

“Such extension shall only be given for such time in which a material part of the Work on the Critical Path of the Project<br />

Schedule cannot be performed, and during which time Contractor utilizes its best efforts to perform all other Work able<br />

to be performed so as to mitigate any delays in the overall completion of the Project. Extensions of time for inclement<br />

weather will not be granted unless such inclement weather causes a delay in the Critical Path of the Project Schedule in<br />

accordance with Paragraph 15.1.5.2."<br />

Add Subparagraph 8.3.1.1 as follows:<br />

8.3.1.1 It is expressly understood and agreed by and between the Contractor and the Owner that the Contract Time as<br />

contained in the Agreement is a reasonable time for the completion of the Work under this Agreement, taking<br />

into consideration recent climatic conditions, and the usual industrial conditions prevailing in the location of<br />

the Project. The Contract Time includes the assumption that there will be at least _____________ (__) days<br />

during which Work on the Critical Path of the Project Schedule cannot be performed because of inclement<br />

weather (the “Assumed Inclement Weather Days”). No Claim in accordance with Paragraph 8.3.1 for an<br />

increase in the Contract Time due to inclement weather (including, without limitation any extension in the<br />

Contract Time for purposes of calculating liquidated damages under Paragraph 3.3 of the Standard Form of<br />

Agreement Between Owner and Contractor) may be made until _______________ (__) days have occurred in<br />

which a material part of the Work on the Critical Path of the Project Schedule could not be performed because<br />

of inclement weather. Provided however, within thirty (30) days of execution of this Agreement, Contractor<br />

shall provide for Owner’s reasonable approval a month-by-month allocation of the Assumed Inclement<br />

Weather Days. Owner and Contractor shall make good faith efforts to reach an agreement on such allocation<br />

and in the event of such agreement, extensions of time in accordance with Paragraph 8.3.1 for inclement<br />

weather will be allowed only if, during any month, inclement weather causes a delay in the Critical Path of the<br />

Project Schedule in excess of the number of days allocated for that month.<br />

ARTICLE 9<br />

PAYMENTS AND COMPLETION<br />

9.2 In the second line after the word “…Architect…” insert the words “…and Owner...” In the fourth line after the<br />

word “…Architect…” when it first appears insert the words “…and Owner...” and after the word "Architect" when it<br />

second appears insert the words "…or Owner."<br />

9.3.1.1 Add the following at the end of Subparagraph 9.3.1.1:<br />

“Contractor shall submit sufficient line item detail to allow the Owner to accurately determine completion for changes in<br />

the Work which has been properly authorized by Construction Change Directives.”<br />

9.3.4 Add Paragraph 9.3.4 as follows:<br />

NAPA CENTURY CENTER XD 12<br />

#165582