6. Final test report forms to be used.<br />

7. Detailed step-by-step procedures for TAB work for each system and issue: terminal flow<br />

calibration (for each terminal type), diffuser proportioning, branch/sub-main proportioning,<br />

total flow calculations, rechecking, diversity issues, expected problems and solutions, etc.<br />

Criteria for using air flow straighteners or relocating flow stations and sensors will be<br />

discussed.<br />

8. List of all air flow, water flow, sound level, system capacity and efficiency measurements to<br />

be performed and a description of specific test procedures, parameters, formulas to be used.<br />

9. The identification and types of measurement instruments to be used and their most recent<br />

calibration date.<br />

10. Specific procedures that will ensure that the air side is operating at the lowest possible<br />

pressures and provide methods to verify this.<br />

11. Details of how building static and exhaust fan/relief damper capacity will be checked.<br />

12. Proposed selection points for sound measurements and sound measurement methods.<br />

13. Details of all exhaust fan balancing and capacity verifications, including any required room<br />

pressure differentials.<br />

14. Plan for hand-written field technician logs or discrepancies, deficient or uncompleted work by<br />

others, contractor interpretation requests and lists of completed tests (scope and frequency).<br />

15. Plan for formal progress reports (scope and frequency).<br />

16. Plan for formal deficiency reports (scope, frequency and distribution).<br />

17. The TAB field technicians shall keep a running log of events and issues. Submit hand-written<br />

reports of discrepancies, deficient or uncompleted work by others, contract interpretation<br />

request and lists of complete tests to the Commissioning Agent and CM/GC at least weekly.<br />

18. Communicate in writing to the Controls Contractor all set points and parameter changes<br />

made or problems and discrepancies identified during TAB, which affect the control system<br />

setup and operation.<br />

19. Provide a draft TAB report within two weeks of completion. A copy will be provided to the<br />

Commissioning Agent. The report will contain a full explanation of the methodology,<br />

assumptions and the results in a clear format with designations of all uncommon<br />

abbreviations and column headings. The report should follow the latest and most rigorous<br />

reporting recommendations by AABC, ASHRAE Standard 111.<br />

20. Provide the Commissioning Agent with any requested data, gathered, but not shown on the<br />

draft reports.<br />

21. Provide a final TAB report of the Commissioning Agent with details, as in the draft.<br />

22. Conduct functional performance tests and checks on the original TAB as specified for TAB in<br />

Division 1 and 15.<br />

D. Architect, Owner, Electrician and Mechanical Engineer: Refer to Division 1.<br />

E. Automatic Temperature Control System (ATCS) Contractor: Refer to Division 1 and 16.<br />

1.03 RELATED WORK<br />

1. ATC Contractor is responsible to act as a Commissioning Agent team member and issue to<br />

the Commissioning Agent for review and comment, their pre-functional plan (point to point<br />

and start-up) and be onsite and available to perform all required system commissioning.<br />

2. All ATC/BAS graphics and sequences are to be demonstrated to the Commissioning Agent<br />

prior to functional testing.<br />

A. Refer to Division 1 for a listing of all sections where commissioning requirements are found.<br />

B. Refer to Division 1 for sections involving related commissioning work; for functional testing<br />

requirements, and preliminary Commissioning Agent Plan.<br />

1.04 COMMISSIONED SYSTEMS<br />

A. The following systems and equipment (including all integral equipment controls) will be commissioned<br />

in this project. All general references to equipment in this document refer only to equipment that is to<br />

be commissioned.<br />

HVAC System<br />

Cinemark 15995 - 3 MECHANICAL SYSTEMS COMMISSIONING<br />

South Napa Century Center XD 12 EnviroDesign, Inc., Bid Issue 7-7-11