Document 00800<br />

Page 5<br />

7.1.4 At any time, the Owner may, through its Architect, without invalidating the Contract, order extra Work or make<br />

scope changes by altering, adding, or deduction from the Work. However, no extra Work or scope change shall<br />

be made unless pursuant to a written Change Order or Construction Change Directive singed by Owner and<br />

Contractor. Furthermore, if the Contractor, without obtaining prior written authorization of the Owner,<br />

performs any additions, deletions, or changes in the Work, the Contractor shall be liable for the entire cost<br />

thereof, or for the removal thereof and restoration to the before-change condition, and shall further be liable for<br />

any expense incurred by other contractors, agencies, or the Owner in adjusting their Work due to changes<br />

initiated by the Contractor.<br />

Add Paragraph 7.2.2 as follows:<br />

7.2.2 The fee agreed upon for scope changes in the Work shall constitute the full overhead and profit charged for<br />

said change in the Work. Change Orders for scope changes shall not include any claim for extended general<br />

conditions or indirect costs such as additional supervision, temporary facilities, field overhead, or any impacted or<br />

consequential damages caused by, or in any way the consequence of, said change in the Work, unless Contractor can<br />

clearly demonstrate that the change has caused an impact on the general conditions cost or the Critical Path<br />

Schedule for the Project. Furthermore, Contractor agrees to make no additional claim for extra costs or extensions of<br />

Contract time within the scope of an agreed Change Order once a Change Order is signed.<br />

Add Paragraphs 7.2.2.1 and 7.2.2.2 as follows:<br />

7.2.2.1 Should Contractor claim any additional costs or delays for any other reason other than for a Scope Change,<br />

such additional cost or delay shall be deemed a claim and will be agreed upon by Change Order or Construction<br />

Change Directive in accordance with Article 15, Claims and Disputes of the General Conditions and<br />

Supplementary Conditions of the Agreement as modified herein. All claims for costs for extended general<br />

conditions, and/or indirect costs such as supervision, temporary facilities, and field overhead, plus any costs for<br />

impacted damages, whether real or consequential, shall be included therein. All such claims for additional costs<br />

or delays must be made within twenty-one (21) days of the cause of the claim for additional costs or delays;<br />

otherwise, such claims shall be deemed to be waived. No additional claims for extra costs or extension of<br />

Contract time within the scope of a specific claim will be allowed once a Change Order for the claim is signed.<br />

7.2.2.2 Change Order Work for claims pursuant to subparagraphs 7.2.2.1 preceding will be performed at cost;<br />

and no increase to the Contract Sum for the Work shall be allowed for increased or extended general conditions, and/or<br />

indirect costs such as supervision, temporary facilities, and field overhead, nor any costs for impacted damages<br />

whether real or consequential; nor any cost for Contractor’s overhead and profit (fee) unless specifically authorized<br />

in writing by the Owner.<br />

Add Subparagraph 7.3.3.5 as follows:<br />

7.3.3.5 Determination by the above methods shall not include any costs for any extended or impacted general<br />

conditions; and/or indirect costs such as supervision, temporary facilities, and field overhead, nor any costs for<br />

impacted damages whether real or consequential unless it is demonstrated by Contractor that Contractor’s<br />

general conditions and indirect costs or construction schedule is so impacted, and then only upon submittal of<br />

supporting costs with sufficient detail to allow analysis by the Owner.<br />

7.3.5 In the second line after the word “…Architect…” insert the words “…and Owner…”<br />

7.3.7 In the second line delete the word “…determine…” and insert the word “…recommend…” In the sixth line<br />

delete the word “…prescribe…” and insert the word “…recommend…”<br />

Add Subparagraph 7.3.7.6 as follows:<br />

7.3.7.6 Costs for items 7.3.7.1 through 7.3.7.5 above shall only be allowed if Contractor can clearly demonstrate to the<br />

Owner that the change impacts Contractor’s costs accordingly.<br />

7.3.8 In the second line delete the word “…Architect…” and insert the word “…Owner…”