2.08 SIGNS<br />

A. Approved enameled metal signs shall be securely attached at all main drains, auxiliary drains,<br />

inspectors' test connections and control valves.<br />

2.09 DETECTOR CHECK VALVE<br />

A. Detector check valve shall consist of an automatic compound lever valve and an external bypass with<br />

disc type water meter, gate valve, check valve and necessary fittings.<br />

B. The detector check valve shall be installed in accordance with the Local Fire Department and Local<br />

Water Department rule and regulations.<br />

2.10 FIRE HOSE VALVE CABINET: Not Used<br />

2.11 FIRE EXTINGUISHER CABINET: Not used, refer to the architectural specifications<br />

PART 3 - EXECUTION<br />

3.01 EXCAVATION AND BACKFILL<br />

A. All trenches shall be dug to a line and the bottom cleaned and shaped to provide support of the pipe<br />

through its entire length.<br />

B. Bracing shall be provided as necessary to maintain excavations.<br />

C. As soon as underground work has been completely installed and tested, all excavations shall be<br />

backfilled with gravel to 1'-0" of finished grade and with clean earth (free from bricks, rocks, cinders,<br />

or any foreign matter) to grade.<br />

D. Minimum depth of the top of pipe shall be 5'-0" below grade.<br />

E. Backfill below concrete or asphaltic slabs shall be gravel to paving based.<br />

3.02 UNDERGROUND PIPING<br />

A. All bends and tees in underground piping shall be provided with concrete thrust blocks of sufficient<br />

size to prevent rupture of joints due to movement of pipe.<br />

B. All underground piping shall be installed in accordance with NFPA-24, 1987, Standard for Outside<br />

Protection.<br />

C. All underground piping shall be flushed in accordance with NFPA-24, 1987, Standard for Outside<br />

Protection.<br />

3.03 SPRINKLER PIPING<br />

A. It shall be a specific requirement that insofar as possible, all sprinkler system mains and branches<br />

shall be installed as close as possible to the structural members, not the ceiling.<br />

B. All piping for all systems shall be coordinated with lighting fixtures, air conditioning ducts, piping and<br />

air diffusers. The coordination shall be made with the sheet metal shop drawings and reflected on the<br />

sprinkler shop drawings prior to submission for approval.<br />

C. Pipe shall be protected from freezing where it might occur as determined by the final pipe routing.<br />

D. No piping shall penetrate the demising walls between auditoriums.<br />

E. A corrosive-resistant placard should be placed on each riser, stating the design criteria and resulting<br />

demand at the base of the riser, including hose stream allowance.<br />

F. All sprinkler piping with welded outlets or connections should be inspected prior to the installation to<br />

ensure that the pipe is free of welding slag and cutouts, and that the welded fittings do not protrude<br />

into the path of the water flow.<br />

G. All piping to be supported from structure, not deck or concrete slab.<br />

Cinemark 15300 - 6 Fire Protection<br />

South Napa Century Center XD 12 EnviroDesign, Inc., Bid Issue 7-7-11