Document 00800<br />

Page 3<br />

"All such claims for concealed conditions encountered must be made within twenty-one (21) days of the first observance<br />

of the concealed condition; otherwise, such claims shall be deemed to be waived. Such claims shall be limited by the<br />

Contractor’s representations in Section 3.2.1."<br />

3.7.5 In the fourth line after the word "any" add the words "commercially reasonable".<br />

3.9.2 Delete this paragraph and replace with:<br />

"Contractor will be required to maintain the same on-site superintendent/project manager throughout the performance of<br />

the Work. Any change in on-site superintendent or project manager will require prior written approval of the Owner.<br />

Owner reserves the right to cause the Contractor to remove and replace any persons in a superintendent or project<br />

manager position whose performance is found to be lacking or objectionable to Owner."<br />

3.9.3 Delete this paragraph.<br />

3.10.2 In the second and third lines before the word “…Architect's…” insert the words “Owner and”. In the fourth<br />

line before the word “Architect” insert the words “…Owner and…”<br />

Add Paragraph 3.10.4 as follows:<br />

3.10.4 Contractor agrees to incorporate into Contractor’s Construction Schedule any scheduling information furnished<br />

by Owner with respect to the requirements of Work as performed on the site by other contractors, vendors, and<br />

material suppliers under separate contract with Owner for the purpose of coordination between Contractor and<br />

Owner’s forces.<br />

Add Paragraph 3.11.1 as follows<br />

3.11.1 The Contractor shall maintain at the site and shall turn over to the Owner upon completion of the Work the<br />

Building Department-stamped permit set of documents.<br />

Add Paragraph 3.12.11 as follows:<br />

3.12.11 Shop drawings, product data, and samples shall be furnished with adequate lead time to allow the Contractor to<br />

process and Architect to approve said documents prior to the time that return of the submittal is required by<br />

subcontractor. Contractor / Architect will require a minimum of ten (10) working days to approve submittals.<br />

Shop drawings not furnished with sufficient lead time for processing and approval shall constitute a Contractorcaused<br />

delay.<br />

Add Paragraph 3.13.1 as follows:<br />

3.13.1 Contractor shall coordinate and cooperate with the Owner relative to portions of the site or structures needed to<br />

be utilized by other contractors, vendors, and material suppliers employed by Owner.<br />

3.14.1 Add the following sentence at the end of this paragraph: "Finished surfaces which appear as damaged, altered,<br />

retrofitted, or otherwise do not appear as “new” construction may be grounds for rejection by the Owner or Architect."<br />

Add Paragraphs 3.15.3 and 3.15.4 as follows:<br />

3.15.3 Contractor shall cause its subcontractors/vendors/material suppliers to clean up all debris created by their work<br />

as the job progresses. Should Contractor, subcontractors, vendors, or material suppliers fail to remove debris<br />

and/or material created or left by their work after forty-eight (48) hours’ written notice to do so, the Owner<br />

reserves the right to remove debris and/or material, clean the premises, and charge the Contractor accordingly.<br />

3.15.4 Contractor shall assume responsibility for dust control during the performance of its Work. The Contractor<br />

shall assume liability for all claims related to dust attributable to its work.<br />

NAPA CENTURY CENTER XD 12<br />

#165582