satisfaction of the Architect and the Owner for a period of one day. Should any element of<br />

the system not perform properly, the Contractor shall make all required corrections, and the<br />

test shall be repeated until successfully performed.<br />

B. Instruments: The Contractor shall provide all instruments, materials and labor to perform the tests and<br />

to obtain and record the measurements specified herein, including the furnishing of all required record<br />

forms as approved by the Architect.<br />

C. The HVAC Contractor shall furnish to the TAB Contractor complete shop drawings and catalog data<br />

for all air moving equipment and apparatus, including fan curves.<br />

D. The HVAC contractor shall install new filters and filter media prior to the final air balance. Filters<br />

are to be MERV 13 filtration required for return and supply. Provide product<br />

data submission for filtration media.<br />

E. The test and balance contractor shall perform all tests and generate reports required by the governing<br />

authorities for all life safety and HVAC systems, including, but not limited to smoke detectors and<br />

combination fire/smoke dampers, etc.<br />

3.04 Final Test and Balance Report<br />

A. Proposed forms and the qualifications of the TAB contractor, including AABC/NEBB Certification<br />

proposed by the Contractor shall be submitted to the Architect for approval at least four weeks prior to<br />

the start of testing. Approval for all of the above shall be obtained prior to the start of testing.<br />

B. Reported Measurements and Data:<br />

1. Electrical: Running amperes and voltage of each motor 3/4 horsepower or larger.<br />

2. Blower speed<br />

2. Static pressure gains or losses at entrance and exit of each filter, coil, fan and damper.<br />

3. Air temperatures in each heated or air conditioned space, at the entrance and exit of each<br />

coil, and unit, downstream from each pair of dampers where air of two different<br />

temperatures is mixed and outside the structure.<br />

4. Air flows at each fan.<br />

5. Air flows at each grille, register, and diffuser.<br />

6. Maximum and minimum air flows at each terminal box.<br />

7. V-Belt drive: driven sheave diameter and RPM; motor sheave diameter and RPM; belt size<br />

and quantity; and center to center distance, maximum, minimum and actual.<br />

C. Presentation of the report shall be four neatly bound copies of a typed report of the final operating test<br />

shall be submitted to the Architect for approval and subsequent transmittal to the Owner.<br />

D. The report shall include a title page stating the following information: TAB Company name, company<br />

address, company telephone and fax numbers, project name, project location, General Contractor<br />

Name, Certifying TAB Engineer.<br />

E. The report shall be sealed by an engineer registered in the state in which the project is<br />

constructed.<br />

3.04 FINAL JOB MEETING:<br />

A. At job completion, all Division 15 and 16 representatives shall meet at the job site and shall jointly<br />

inspect, check and test each control circuit, interlock circuit and power circuit to each piece of<br />

equipment. The Architect, Engineer and Owner shall be advised in writing of the time and date of this<br />

inspection in sufficient time to allow them to make arrangements to have a representative present if<br />

desired.<br />

END OF SECTION<br />

Cinemark 15034 - 1 HVAC Test & Balance<br />

South Napa Century Center XD 12 EnviroDesign, Inc., Bid Issue 7-7-11