transparencies. Enter thereon, in a neat and accurate manner, a complete record of all revisions of<br />

the original drawings, as actually installed. All revisions are to be identified in a professional manner<br />

equal to the presentation of the original Contract Documents; however all deviations shall be clearly<br />

identified. Submit one (1) set of vellum transparencies and black and white prints of these revised<br />

transparencies to the Engineer for review. The cost for transparencies and for making required<br />

changes to be borne by the appropriate Subcontractor.<br />

3.04 PRODUCT DELIVERY, STORAGE AND HANDLING<br />

A. The Contractor shall follow the manufacturer's directions completely in the delivery, storage and<br />

handling of equipment and materials.<br />

B. Equipment and materials shall be tightly covered and protected against dirt, water, chemical or<br />

mechanical injury and theft. At the completion of the work, fixtures, equipment and materials shall be<br />

cleaned and polished thoroughly and shall be in a condition satisfactory to the Architect.<br />

C. Coordinate with Section 01352 IAQ Management"<br />

3.05 UTILITIES, REGULATIONS, METERS<br />

A. Locations and elevations of utilities have been obtained from shell building drawing or to other<br />

sources and are offered as a general guide only, without guarantee as to accuracy. The Contractor<br />

shall verify the exact location and elevation of utilities and their relation to the work before entering<br />

into a contract.<br />

B. The Contractor shall arrange with the landlord and utility companies for service connections, purchase<br />

of meters and vaults, verifying locations and patching pavements, sidewalks, and other surfaces, and<br />

restoring them to their original condition.<br />

C. The Division 15 contractor shall be responsible for final connection of domestic water service, storm<br />

system, sanitary system, and fire service to the building utilities.<br />

D, Meters shall be installed in coordination with the project Measurement & Verification<br />

Plan.<br />

3.06 PROTECTION OF WORK AND PROPERTY<br />

A. The Contractor shall take proper precautions to protect adjacent property, as provided by law and the<br />

Contract Documents, with which his work comes in contact, or over which he may have occasion to<br />

transport, hoist or move materials, equipment debris, etc., and shall satisfactorily repair and make<br />

good any damages caused by him during construction operations.<br />

B. The Contractor shall provide and maintain suitable temporary sidewalks, fences or other structures as<br />

required by law, or as otherwise necessary for the protection of workmen and passersby and as<br />

necessary to prevent obstruction or interference with traffic in public streets or sidewalks, or private<br />

right-of-way. He shall leave access to all fire hydrants, provide temporary walkways around any<br />

obstructions made in any public place on account of his work and maintain sufficient lights and<br />

barricades to protect passersby at night. All streets, curbs and sidewalks shall be maintained in good<br />

condition and so left at the completion of the work. The Contractor shall make all necessary<br />

arrangements and perform all services required in connection with or as occasioned by his work for<br />

the care, protection and maintenance of all public utilities, including fire hydrants, pipe lines and<br />

electrical and/or telephone, telegraph and all other items of similar character on or adjacent to the<br />

site, assuming all responsibility and payment of all cost incidental to such care and protection or<br />

rectification of damage done for which the Owner might otherwise be liable.<br />

3.07 CLEANING UP AND REMOVAL OF RUBBISH<br />

A. The Contractor shall be responsible for keeping the premises (including the outside area) free of all<br />

rubbish, debris and waste materials of every kind at all times during the Contract period. This<br />

requirement is mandatory and shall apply regardless of whether such rubbish, etc., accumulates in<br />

consequence of his work of his Subcontractors operations.<br />

3.08 PROTECTIVE COATINGS<br />

Cinemark 15000 - 7 Mechanical General Conditions<br />

South Napa Century Center XD 12 EnviroDesign, Inc., Bid Issue 7-7-11