Section 09950<br />

Page 3<br />

6. Ribs run vertically (parallel to selvage) in auditoriums and vestibules. Joints run horizontally at corridors,<br />

lobbies and mezzanine stair. Joints run parallel to floor on ramps, following the slope and mitering at<br />

angles at top and bottom. Carpet edges are to be covered with tile or corner guards.<br />

B. Installation Procedure<br />

1. Trim edges so as to balance seam between ribs (a very sharp edge must be maintained)<br />

2. Position the striped selvage on left-hand side when cutting and installing.<br />

3. Trim fabric on flat table prior to installing on the wall.<br />

4. Apply heavy-duty pre-mixed vinyl adhesive to fabric with a notched trowel.<br />

5. Install fabric from top to bottom, between two plumb lines for absolute vertical alignment.<br />

6. Fabric should then be firmly pressed to wall using 1/4" nap roller to insure maximum contact between<br />

adhesive and wall.<br />

C. Adhesives<br />

1. Adhesives to be used should be of the heavy duty vinyl type, with low water content, which dry clear or<br />

translucent. If clay base is used cleanliness and workmanship must be maintained.<br />

3.04 COORDINATION OF DRAPERY<br />

A. Preparation:<br />

1. Install blocking at bottom of fabric and around openings as required by Drawings.<br />

2. Install all acoustical insulation prior to initiating sound fold work.<br />

B. Installation of soundfold drapery will be by Cinemark USA.<br />

C. Wood trim shall be furnished and installed by the contractor.<br />

3.05 CLEAN-UP<br />

A. Clean wall coverings of adhesives, dust, dirt, and other contaminants.<br />

B. Remove excess materials and debris from the premises.<br />

C. Replace wall plates and accessories.<br />

3.06 EXTRA STOCK<br />

A. Provide in accordance with Section 01750 - Spare Parts and Maintenance Materials.<br />

B. Provide ten percent (10%) additional wall covering material, of each type, identical to that installed for<br />

maintenance and replacement uses.<br />

END OF SECTION<br />