PART 1 - GENERAL<br />

1.01 SCOPE<br />

A. Provide Wall Covering Work as indicated by the Contract Documents.<br />

B. Work, items and requirements specified elsewhere that apply and/or relate to this Section include:<br />

1. Gypsum Wallboard - Section 09250<br />

2. Tile - Section 09310<br />

3. Painting - Section 09900<br />

4. Prefinished Panels - Section 09985<br />

5. Corner Guards - Section 10260<br />

1.02 STANDARDS<br />

A. Meet requirements and recommendations of applicable portions of the Standards listed.<br />

1. American Society for Testing and Materials ASTM<br />

2. Painting and Decorating Contractors of America PDCA<br />

3. National Fire Protection Association NPPA<br />

NAPA CENTURY CENTER XD 12<br />

#165582<br />

SECTION 09950<br />

WALL COVERING<br />

1.03 SUBMITTALS<br />

A. NO SUBSTITUTIONS<br />

B. Provide 12"x12" samples to the Architect.<br />

C. Provide Architect with electronic copies of maintenance instructions for each wall covering.<br />

D. Instructions to contain manufacturer's recommended cleaning and application methods, including precautions<br />

in use of cleaning materials which may be detrimental to surfaces if improperly applied.<br />

D. Recycled Content:<br />

1. Indicate recycled content; indicate percentage of pre-consumer and post-consumer recycled content per<br />

unit of product.<br />

2. Indicate material cost of product less labor included in project.<br />

3. If recycled content product is part of an assembly, indicate the percentage of recycled content product in<br />

the assembly by weight.<br />

E. VOC emissions: Provide product data indicating VOC emissions in grams/liter (g/L).<br />

4. Adhesives and sealants: Comply with California’s South Coast Air Quality Management District<br />

(SCAQMD) #1168 identified in Section 01352.<br />

1.04 DELIVERY AND STORAGE<br />

A. Wallcoverings require a minimum four weeks lead-time.<br />

B. Schedule deliveries to avoid any delay in the work.<br />

C. Store wall covering in clean and dry area where temperatures are maintained at minimum 45 F with normal<br />

humidity. Do not store in upright position.<br />

1.05 ENVIRONMENTAL CONDITIONS<br />

A. Maintain surfaces and materials at minimum 60°F three days before and during application period.<br />

B. Provide adequate and continuous ventilation during work and after installation of wall covering.<br />

C. Wallcoverings must be hung under sufficiently bright light. If existing lighting is not sufficient, installerwiall<br />

supply supplementary lighting.<br />

1.06 GUARANTEE<br />

A. The Contractor shall guarantee that work executed under this Section will be free from defective materials<br />

and/or workmanship for a period of one year from the date of Substantial Completion.<br />

B. The Contractor further agrees that he will, at no expense to the Owner, repair and replace such defective work<br />

and other work damaged thereby, which becomes defective during the guarantee period.<br />

1.07 MANUFACTURER'S REPRESENTATIVES<br />

A. Refer to drawings.<br />

PART 2 - PRODUCTS<br />

2.01 MATERIALS<br />

A. Provide wallcovering types as shown in the finish schedule at locations described in the Drawings: