Document 00300<br />

Page 5<br />

Start plumbing/electrical underground rough in 27<br />

Submittal deadline to architect (60 days from N.T.P.) 25<br />

Complete foundations 25<br />

* Start steel erection 23<br />

Start mezzanine concrete pours and framing 20<br />

* Start roof installation 19<br />

Start HVAC ducts in auditoriums and mezzanine 19<br />

Set roof top unit curbs 20<br />

Start exterior building painting 17<br />

* Complete all masonry work 16<br />

Start auditorium ceilings 16<br />

* Complete roof installation 16<br />

Complete all slab on grade concrete 15<br />

Set roof top HVAC units 15<br />

EMS vendor installs communication wire to roof top units 15<br />

* Permanent power 10<br />

Complete mezzanine mech./elec. (incl. proj. exhaust) 9<br />

Complete mezzanine ceilings and wall finishes 9<br />

Complete mezzanine doors and hardware 9<br />

Complete mezzanine floor vct (wax and seal) 9<br />

* Telephone service to building 8<br />

Start ceramic tile install (restrooms are first priority) 9<br />

Complete wall carpet at auditorium pilasters 8<br />

* Mezzanine 100% complete 8<br />

Telephone and security vendors pull lines at mezzanine 8<br />

Start auditorium wall carpet 8<br />

* 1/2 auditoriums complete 8<br />

* Auditorium drape/screen installation window opens 7<br />

* Projection consoles deliver 7<br />

Measure for millwork install (concessions drywalled) 8<br />

Complete steel erection 8<br />

Complete exterior building painting 8<br />

Start corridor wall vinyl and wall carpet 7<br />

* Balance of auditoriums complete 7<br />

Complete pouring auditorium risers 7<br />

Start rubber base in auditoriums 6<br />

Start auditorium floor light system 6<br />

Start installation of auditorium handrails 6<br />

Ceilings and tile complete at concession areas 6<br />

Scullery wall, floor, ceiling finishes complete 5<br />

Install CO2 tanks and run flex lines 5<br />

* Install millwork 5<br />

Start drink tower and scullery drink equipment 5<br />

Layout and predrill for auditorium seats 4.5<br />

Start floor carpet (auditoriums and lower level) 4<br />

Scullery food service equipment installs 4<br />

Complete auditorium vct at risers 4<br />

* Seats deliver and install 4<br />

Start exterior and interior signage install 4<br />

EMS panel installs 4<br />

Menu signs, int. postercases, and aud. entrances install 3<br />

Install exterior postercases 3<br />

SLV install begins 3<br />

Complete auditorium floor lights and handrails 2<br />

Final cleaning begins 2<br />

NAPA CENTURY CENTER XD 12<br />