10.03.2015 Views

specs

specs

specs

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Section 02200<br />

Page 3<br />

B. In areas where buildings are proposed the existing fill soils to be over-excavated to undisturbed native ground<br />

as observed and approved by the construction Soil Engineer. It is expected that excavations to elevations<br />

ranging from +1 to +5 feet should be expected resulting in over-excavation depths of 5 to 11 feet (not<br />

including existing stockpiles).<br />

C. Excavations to extend a minimum of 5 feet laterally beyond the building footprint and the area replaced with<br />

engineered fill as noted below.<br />

D. In other areas (non-building or parking lots), the upper 3 feet (minimum) of the subgrade to consist of<br />

engineered fill. Where over-excavation is required (north half of the site), the area should be excavated to a<br />

depth of 2 feet, the bottom 12 inches scarified and compacted in-place, and replaced with engineered fill. The<br />

south half of the site will require more than 3 feet of fill to achieve the design grades and over-excavation is<br />

not expected to be needed.<br />

E. The existing stockpiles which cover a portion of the site must be removed. After removal of existing<br />

stockpiles, the surface of the areas to be graded will require stripping to remove vegetation and/or other<br />

deleterious materials. It is estimated that stripping depths of about 1 to 2 inches may be necessary; however,<br />

the actual depth of stripping to be determined in the field by the construction Soil Engineer. Stripped material<br />

from the site may not be used as engineered fill, but may be stockpiled and used later for landscaping purposes.<br />

F. As part of this project, the roadway Hartle Court (old) is to be demolished. Road improvements (including<br />

curb/gutter/sidewalk) and any utilities which will not remain in service must be demolished and removed from<br />

the site. The exception is that the aggregate base, asphalt concrete and Portland cement concrete may be<br />

crushed and used on the site as general fill.<br />

G. Any conflicting utilities which run through the site must be abandoned and/or relocated.<br />

H. Satisfactory materials acceptable for filling and backfilling work may be temporarily stockpiled on site.<br />

I. Make excavations large enough to permit placing and removal of shoring, forms, and for inspection of the<br />

work.<br />

J. Excavation for Structures:<br />

1. Level bottoms of trenches reasonably level. Change elevation at right-angled steps with forms or<br />

bulkheads. Step trenches in 8-inch maximum depth and 24-inch minimum length increments.<br />

2. Fill excess depth in trench excavations with concrete. Form excess width in size, or fill with concrete.<br />

3. Surfaces of excavations shall be within one inch per foot and any excessive depth in excavations shall be<br />

filled with lean concrete.<br />

K. Remove all excess excavated material from the job site.<br />

3.03 BACKFILLING<br />

A. Backfilling includes filling and compaction beneath slabs and structural concrete; against and around concrete<br />

foundation walls after forms have been removed and foundation inspection completed.<br />

B. Native clay soil subgrade may be soft, wet and unstable making placement of fill with conventional<br />

earthmoving equipment difficult. A stabilization layer of fill maybe required at the bottom of the excavations.<br />

Stabilization layer to consist of Tensar BX1200 (or approved equivalent) geogrid overlain by an 18 inch thick<br />

layer of 6 inch minus crushed rock overlain by Mirafi 600x (or approved equivalent) geotextile followed by<br />

engineering fill placement. The requirement for stabilization and the method may be modified in the field by<br />

the construction Soil Engineer.<br />

C. Do not start backfilling operations until foundation drainage system and waterproofing have been reviewed and<br />

tested.<br />

D. After stripping and over-excavation of existing firm and loose fills, and prior to any additional fill placement,<br />

the upper 12 inches should be scarified, moisture conditioned as necessary and compacted to a minimum<br />

degree of relative compaction of 90% at 2 or more percent above optimum moisture content as determined by<br />

ASTM D1557 Laboratory Test Procedure. Mitigation of wet/unstable soils is discussed above.<br />

E. Just prior to placement of select fill, all traces of organic, loose or obviously compressible material must be<br />

removed.<br />

F. Ensure areas are free from debris, snow, ice and water, and that ground surfaces are not in frozen condition.<br />

G. Backfill areas to grades, contours, levels, and elevations indicated.<br />

H. Backfill systematically and as early as possible to allow maximum time for natural settlement and compaction.<br />

NAPA CENTURY CENTER XD 12<br />

#165582

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!