PART 1 - GENERAL<br />

SECTION 02200<br />

EARTHWORK<br />

1.01 SCOPE<br />

A. Provide Earthwork as indicated by the Contract Documents including the following:<br />

1. Layout of building lines.<br />

2. Grading for building pad preparation.<br />

3. Excavating for structures<br />

4. Trenching for utilities<br />

5. Filling, backfilling and compacting<br />

6. All work shall follow requirements listed in the geo-technical report included herein as Appendix A.<br />

B. Work, items and requirements specified elsewhere that apply and/or relate to this Section<br />

include:<br />

1. Geotechnical Information – Appendix A<br />

2. Summary of Work - Section 01010<br />

3. Testing - Section 01410<br />

4. Structural Concrete - Section 03300<br />

1.02 STANDARDS<br />

A. Meet requirements and recommendations of applicable portions of Standards listed.<br />

1. American Society for Testing and Materials ASTM<br />

2. American Association of State Highway and Transportation Officials AASHTO<br />

1.03 PRECAUTIONS<br />

A. Cover holes and trenches when work is not in progress.<br />

B. Work shall be done by experienced operators trained to do this type of work.<br />

C. Avoid damage to underground utilities such as water mains, sanitary sewers, buried cables, etc. which might<br />

extend across or adjoin site.<br />

D. Take special precautions to avoid extending any operations onto adjacent property.<br />

E. If it is necessary to gain access to adjacent property, the Contractor shall be responsible for obtaining right of<br />

access from the adjacent property owners.<br />

F. If there is any damage to the adjacent property caused by these operations, the Contractor shall do all that is<br />

necessary to correct the damages to the adjacent property Owner's satisfaction.<br />

1.04 TESTING<br />

A. All testing of work included in this section will be done by an independent soils testing laboratory to be<br />

selected and paid for by the Contractor. Refer to Section 01410 - Testing Laboratory Services.<br />

B. All test results will be forwarded to the Architect, Structural Engineer, Civil Engineer, Owner, Tenant and<br />

Contractor as soon as practicable, and any work not complying with the Specifications shall be reworked or<br />

replaced until it does comply with specified requirements.<br />

1.05 LAYING OUT<br />

A. Engage a qualified surveyor approved by the Owner to locate the work.<br />

B. Locate bench marks, monuments, and other reference marks for elevation and location of buildings. Notify<br />

Architect of apparent discrepancies in indicated locations.<br />

C. Protect reference points from dislocation or damage. Replace or repair immediately any points damaged,<br />

destroyed or dislocated.<br />

D. Verify location of vertical and horizontal reference points, and verify that the existing grades are as indicated<br />

on the Drawings.<br />

E. Notify the Architect by letter if the existing grades are not as indicated. Any claims for extras for filling and<br />

cutting operations that are not brought to the attention of the Architect by this letter will not be considered and<br />

will have to be corrected at the Contractor's expense.<br />

F. Accurately locate buildings and building limit lines on site according to Contract Documents and coordinate<br />

this work with other contractors on the site.<br />