PART 1 GENERAL<br />

1.01 SECTION INCLUDES<br />

SECTION 02223 - MINOR DEMOLITION FOR REMODELING<br />

A. Removal of designated construction.<br />

B. Disposal of materials.<br />

1.02 RELATED SECTIONS<br />

A. Section 01100 – Summary of Work: Work sequence and continued occupancy of the building.<br />

B. Section 01500 - Temporary Facilities and Controls: Temporary enclosures.<br />

C. Section 01700 - Execution Requirements: Closeout Submittals: Project record documents.<br />

1.03 REFERENCES<br />

A. American National Standards Institute:<br />

1. ANSI A10.6: “Safety Requirements for Construction and Demolition”.<br />

B. National Fire Protection Association:<br />

1. NFPA 241: “Safeguarding Construction, Alteration, and Demolition Operations”.<br />

1.03 REGULATORY REQUIREMENTS<br />

A. Conform to applicable code for demolition work, dust control, products requiring electrical<br />

disconnection and re-connection.<br />

B. Obtain required permits from authorities.<br />

C. Do not close or obstruct egress from any building exit or site exit without specific approval from<br />

the Owner and municipal authority.<br />

D. Do not disable or disrupt building fire or life safety systems without 3 days' prior written notice to<br />

Owner and without specific approval from the municipal authority.<br />

E. Comply with hauling and disposal regulations of authorities having jurisdiction.<br />

F. Conform to applicable regulatory procedures when hazardous or contaminated materials are<br />

discovered.<br />

1.04 QUALITY ASSURANCE<br />

A. Use adequate numbers of skilled workers who are thoroughly trained and experienced in the<br />

necessary trades and who are completely familiar with the specified requirements and methods<br />

needed for proper performance of the work of this section.<br />

B. Comply with ANSI 10.6 and NFPA 241.<br />

1.05 SCHEDULING<br />

A. Schedule work under the provisions of Section 01300.<br />

B. Schedule work to coincide with new construction and phasing.<br />

1.06 PROJECT CONDITIONS<br />

A. Conduct demolition to minimize interference with adjacent and occupied building areas.<br />

1. Conduct selective demolition and debris-removal operations to ensure minimum<br />

interference with roads, streets, walks, walkways, parking lots, and other adjacent<br />

occupied and used facilities.<br />

B. Cease operations immediately if structure appears to be in danger and notify Architect. Do not<br />

resume operations until directed.<br />

04-27-11 MINOR DEMOLITION FOR REMODELING<br />

02223 -1