SECTION 01100 – SUMMARY OF WORK<br />

PART 1—GENERAL<br />

1.01 SUMMARY OF WORK<br />

A. Project Identification:<br />

1. Project: <strong>Buffalo</strong> <strong>Wild</strong> <strong>Wings</strong> Grill & Bar<br />

The Pavilions At Talking Stick<br />

New Development District<br />

8870 East Indian Bend Road<br />

Scottsdale, AZ 85250-8525<br />

B. Contract Documents, prepared by the Architect, GHA Architecture/Development<br />

C. The Work consists of a total square footage as described in the Contract Documents.<br />

D. All Work shall be constructed in accordance with all applicable codes and regulations. Work<br />

shall be installed in accordance with generally accepted standards of construction and in strict<br />

accordance with manufacturer’s printed instructions and specifications whether specifically<br />

detailed in the Contract Documents or not.<br />

E. Contractor shall maintain Owner and Landlord required insurance and Workers’ Compensation<br />

at all times and furnish proof of same to Owner prior to start of construction.<br />

F. Work Not Included: The following will be provided by others:<br />

1. See the Comprehensive Equipment Schedule and Project Responsibility Matrix on<br />

Drawing G001, which designates responsibility for furnishing and installing the various<br />

items included in the Project, as well as final connections.<br />

1.02 WORK / SITE RESTRICTIONS<br />

A. Contractor shall comply with all building Owner’s standards.<br />

B. Contractor’s Use of Premises: During construction, Contractor shall have full use of the site.<br />

Contractor’s use of premises is limited only by Owner’s right to perform work or employ other<br />

contractors on portions of Project and as follows:<br />

1. On-Site No Smoking Policy: As designated below, the Contractor will be responsible to<br />

maintain a No Smoking Policy on site. This policy will include the Contractor’s personnel,<br />

subcontractors, material delivery personnel and all other field people on site. There will be<br />

no smoking permitted on site after the following time periods. This No Smoking Policy will<br />

be strictly enforced.<br />

a. There will be no smoking on the roof area after the roofing materials are installed.<br />

b. There will be no smoking inside the building area after the building has been<br />

enclosed. This will commence when the exterior openings have been enclosed and<br />

the insulation and drywall installation begins.<br />

PART 2—PRODUCTS<br />

Not used<br />

PART 3—EXECUTION<br />

Not used<br />

END OF SECTION<br />

04-27-11 SUMMARY OF WORK<br />

01100 -1