out of water. Provide volume control shutoff valve, bimetal dial thermometer, brass pipe,<br />
fittings, and unions mounted to exposed cabinet panel; bottom supplies; top outlet. ½”<br />
bypass; minimum 1.0” gpm @ 10 psi drop and set at 40 gpm @ 10 psi drop; 120°F<br />
discharge temperature. Other acceptable manufacturers: Lawler, Bradley.<br />
PART 3. – EXECUTION<br />
3.1 A. Slope water piping 1” per 40’ and arrange to drain at all low points.<br />
B. All storm and sanitary piping sloped 1/8” per foot unless noted otherwise or if required to<br />
meet inverts. Notify engineer of any changes.<br />
C. All underground sewer pipe within 10 feet of buried water supply piping shall be<br />
constructed in accordance with State and/or Local Code.<br />
D. Provide all appropriate sanitary piping fittings, wyes and bends. No double-wye fittings for<br />
sanitary drainage in horizontal position shall be used.<br />
E. Vent pipes passing through roofs shall terminate at least 12” above the roof line.<br />
F. Above grade plastic drain and vent piping horizontal and vertical runs cannot exceed 35<br />
feet. Solvent welds shall be done with a contrasting primer to the color of the pipe and<br />
cement. Plastic piping shall not be installed in air plenum spaces including parking<br />
garage area.<br />
G. Contractor shall provide all sleeves required through footings, foundation walls and floors.<br />
Underground services shall be sleeved with schedule 40 PVC sleeving. Sleeve to be (1)<br />
size larger than the pipe it serves. Extend sleeves 0-3” beyond penetration. Coordinate<br />
with Structural Engineer.<br />
H. Provide shut-off valves as required by Code and good installation practice for the proper<br />
isolation of equipment. All branch take offs shall have isolation shut off valves. Provide<br />
extended stem valves where required for insulation. Except as otherwise specified or<br />
shown on plans, valves 2-1/2 inch and smaller shall have screwed end connections and<br />
valves 3 inch and larger shall have flange end construction. Install manual drain valves at<br />
every low point of each water piping system.<br />
I. Mechanical formed tees connections as created by T-Drill or approved equal shall be<br />
formed in a continuous operation consisting of drilling a pilot hole and drawing out the<br />
surface to form a collar having a height of not less than three times the thickness of the<br />
tube wall. Branch tube shall not obstruct the flow in the main line tube. All joints shall be<br />
brazed in accordance with the Copper Development Association. Soft soldered joints will<br />
not be permitted. Mechanical formed connections shall be listed by the International<br />
Plumbing Code, B.O.C.A., l.A.M.P.O., S.B.C.C., ASME Code for Pressure Piping and<br />
shall be acceptable to governing authorities.<br />
J. All threaded nozzle fixtures to have atmospheric vacuum breakers.<br />
K. Installation of cross connection control devices and related valves shall maintain 1 ‘-6”<br />
clear from wall or other obstructions, no more than 5’-O” above floor or closer than 2’-O”<br />
from floor.<br />
06/25/09 PIPING MATERIALS AND METHODS<br />
15150-4