3. The cost for mechanical CAD drawing files, provided in AutoCAD, will be $50.00<br />
per sheet payable directly to Engineer of Record CAD files will be sent via email<br />
only.<br />
1.3 COORDINATION OF DRAWINGS<br />
A. Contractor shall submit a ¼-inch scale drawing to the Engineer indicating placement of all<br />
mechanical and electrical systems and equipment. Indicate proposed locations of all<br />
major equipment and materials, including but not limited to service equipment, exterior<br />
wall and foundation penetrations, fire-rated wall and floor penetrations, sizes and location<br />
of required concrete pads and bases, and mechanical/electrical equipment room layouts.<br />
This effort will require each trade to closely work together to produce a ¼=1’-0” set of<br />
coordination drawings for each area of the building.<br />
B. Coordinate scheduling and sequencing required for movement and positioning of large<br />
equipment into the building with all other Contractors to minimize impact on their work.<br />
C. This Contractor shall provide any and all input required to complete these drawings.<br />
1.4 MATERIALS AND EQUIPMENT<br />
A. Materials:<br />
1. All materials shall be new and of the type and quality specified herein.<br />
2. Specific materials and equipment specified is intended to establish a minimum<br />
standard of required quality. Where specified materials and equipment fail to<br />
meet minimum standards of existing federal, state and local codes and<br />
ordinances, the governing codes and ordinances shall prevail.<br />
3. The Contractor shall provide all minor miscellaneous materials necessary for the<br />
complete mechanical installation.<br />
4. For materials and equipment specified by description only, the Contractor shall<br />
provide materials or equipment suitable for the purpose intended. These shall be<br />
in conformance with all governing codes, these Specifications and normal trade<br />
practice.<br />
5. For materials or equipment specified by manufacturer’s name and catalog<br />
number, the Contractor shall provide the item specified. The Contractor may<br />
submit materials and equipment for prior approval to the Engineer.<br />
6. Supply materials and equipment to the site in original packages, containers or<br />
crates insofar as is practical. It shall be the Contractor’s responsibility to schedule<br />
deliveries in accordance with the overall Project schedule. The Contractor shall<br />
closely coordinate all deliveries with other Contractors.<br />
7. Provide for proper receipt, handling, storage, and protection from the elements<br />
for all materials and equipment to be used on this Project so as to effectively<br />
prevent damage or deterioration. Materials or equipment sustaining damage or<br />
undue deterioration from any cause whatsoever shall be replaced or repaired by<br />
Contractor as required by the Engineer.<br />
06/25/09 MECHANICAL GENERAL CONDITIONS<br />
15010-3