Undiluted Reserves at $550 per Ounce Gold<br />
Overburden Tonnes 12,100,000<br />
Oxide Below 0.15 g/tonne* 11,100,000<br />
Subtotal, Waste Rock 23,200,000<br />
In-Pit Proven and Probable Reserves<br />
In-Pit Inferred Resources<br />
Cut-off Tonnes Average Cut-off Tonnes Average<br />
Grade Above Grade Grade Above Grade<br />
(g/tonne) Cut-off (g/tonne) Ounces (g/tonne) Cut-off (g/tonne) Ounces<br />
0.15 40,000,000 0.53 680,000 0.15 35,000 0.32 400<br />
Undiluted Reserves at $625 per Ounce Gold<br />
Overburden Tonnes 14,900,000<br />
Oxide Below 0.15 g/tonne* 13,300,000<br />
Subtotal, Waste Rock 28,200,000<br />
In-Pit Proven and Probable Reserves<br />
In-Pit Inferred Resources<br />
Cut-off Tonnes Average Cut-off Tonnes Average<br />
Grade Above Grade Grade Above Grade<br />
(g/tonne) Cut-off (g/tonne) Ounces (g/tonne) Cut-off (g/tonne) Ounces<br />
0.15 46,800,000 0.50 752,000 0.15 <strong>101</strong>,000 0.32 1,000<br />
Undiluted Reserves at $700 per Ounce Gold<br />
Overburden Tonnes 23,700,000<br />
Oxide Below 0.15 g/tonne* 19,600,000<br />
Subtotal, Waste Rock <strong>43</strong>,300,000<br />
In-Pit Proven and Probable Reserves<br />
In-Pit Inferred Resources<br />
Cut-off Tonnes Average Cut-off Tonnes Average<br />
Grade Above Grade Grade Above Grade<br />
(g/tonne) Cut-off (g/tonne) Ounces (g/tonne) Cut-off (g/tonne) Ounces<br />
0.15 58,400,000 0.46 870,000 0.15 131,000 0.30 1,300<br />
* This material must be mined but does not meet the processing cut-off.<br />
Mineral Processing and Metallurgical Testing<br />
Several metallurgical tests on mineralized oxidized material from the Property have been completed, both<br />
by Castle Gold and by independent groups between 2004 and 2006. <strong>The</strong> tests were designed to determine<br />
the leaching characteristics of the oxidized material and consisted of:<br />
• Bottle roll leach tests in 2004 and later column leach tests in 2006 by Kappes, Cassiday and<br />
Associates (“KCA”);<br />
• Two onsite bulk heap leach tests conducted by Castle Gold in 2005, followed by a residual<br />
analysis of the heaps conducted by Metcon Research (“Metcon”) in 2006.<br />
<strong>The</strong> data from the various tests have been reviewed and vetted by, D. Koningen, P.Eng, acting in the<br />
capacity of Castle Gold’s internal Qualified Person in matters of process engineering and metallurgy. Mr.<br />
Koningen is also a Director of Castle Gold. Presently Castle Gold is in the process of completing<br />
v