5.3 Some Examples<br />

5.3 Some Examples<br />

Now that you are familiar with the criteria language and calendar<br />

mechanisms, consider how to apply what you have learned to the following<br />

scheduling problems.<br />

Example 1<br />

To run the Weekend Summary Report on the first workday of the week, which<br />

criteria statement would you use?<br />

Criteria:<br />

WDOW1<br />

Example 2<br />

Now use another variation of WDOW to schedule the Weekly Summary<br />

Report to run on the last workday of the week.<br />

Criteria:<br />

WDOW-1<br />

Example 3<br />

Which criteria statement would you use to run the Monthly Summary Report<br />

on the first workday of the month?<br />

Criteria:<br />

WDOM1<br />

Example 4<br />

Which variation of WDOM will run the Monthly Summary Report on the last<br />

workday of the month?<br />

Criteria:<br />

WDOM-1<br />