EXISTING HOUSE: Ledger cannot attach to cantilevered floor joists or brick faces.<br />
Ledger<br />
Joist span(s)<br />
(A) <strong>Deck</strong> joists<br />
(Show center beam(s) if<br />
multi-span deck)<br />
4x4 or 6x6 posts<br />
2’ - 3’ Cant.<br />
(C) Concrete footing<br />
Post spacing<br />
FRAMING STANDARDS<br />
10” Minimum<br />
run<br />
34” minimum - 38” maximum<br />
7.75 “ max rise measured from stair nose<br />
STAIRS AND GUARDS<br />
Handrail with minimum 1 1/4”<br />
to maximum 2” handgrip required<br />
for 4 or more risers<br />
Approved decking material<br />
36” maximum horizontal<br />
span between PT<br />
Hem Fir stringers. Maximum<br />
3/8” tread & rise<br />
difference<br />
Set beam on post; do not<br />
bolt through. Beams must be<br />
nailed together & all splices<br />
over columns<br />
Post beam connector<br />
Guard openings spaced < 4”<br />
Joists to be nailed to beam with<br />
two(2) 16d or three (3) 8d nails<br />
Minimum 36”<br />
high guard is<br />
required when<br />
deck is > 30”<br />
above grade<br />
NOTE: Screws are not allowed. Tico nails or joist<br />
hanger nails must be used for all hardware.<br />
Rim Joist<br />
Approved weather protection<br />
for ledger board<br />
<strong>Deck</strong> joist<br />
Post is of redwood<br />
or treated<br />
wood.<br />
Post Anchor<br />
6” above grade<br />
Joist hanger attached to ledger<br />
Ledger attached to rim joist per<br />
Table (C) with minimum 5” length<br />
lag bolts<br />
CONNECTION DETAILS<br />
30” Below grade*<br />
*12” deep piers if deck is detached and