09.02.2015 Views

Annexure XIV Continued… - Edelweiss

Annexure XIV Continued… - Edelweiss

Annexure XIV Continued… - Edelweiss

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

costs related to such rehabilitation and resettlement. TRN is required to achieve the COD of the first unit of the<br />

Ratija Project with 65 or 70 months from January 15, 2010.<br />

The IA can be terminated by serving a sixty (60) days notice by the Government in case of an event of default<br />

by TRN or by TRN in the event of a event of default by the Government. The IA can be terminated by either<br />

party or in the event where either party is unable to perform any obligations required to be performed due to<br />

force majeure (as defined in the IA) for a continuous period of eighteen (18) months. TRN can also terminate<br />

the IA, in the event of enactment of any law or regulation or any subsequent act of any Governmental<br />

Instrumentality, which makes the performance of this IA impossible for it.<br />

2. Power purchase agreement dated January 4, 2011 between TRN Energy Private Limited, our<br />

Subsidiary (“TRN”) and Chhattisgarh State Power Trading Company Limited (“CSPTCL”)<br />

TRN has entered into a power purchase agreement dated January 4, 2011 with CSPTCL (“PPA”) for sale of<br />

power from the coal based power project with an installed capacity of 600 MW at Raigarh District, State of<br />

Chhattisgarh (“Raigarh Project”).<br />

As per the PPA, TRN has undertaken to sell to CSPTCL the contracted power i.e. sum of 30% of the aggregate<br />

capacity of the Raigarh Project and 5% of the net power generated by the Raigarh Project on an annualized<br />

basis in accordance with the tariff structure laid down in the PPA. The obligations of TRN include executing<br />

the Raigarh Project in a timely manner so as to enable each of the units and the power station to be<br />

commissioned not later than its scheduled commercial operation date and making available the contracted<br />

output and contracted capacity through the use of prudent utility practices to CSPTCL.<br />

The term of the PPA is for a period of twenty years from the date of commencement of supply of electricity by<br />

TRN to CSPTCL, unless extended in accordance with the PPA. The PPA can be terminated upon the<br />

happening of events of default by either of the parties in accordance with the PPA.<br />

III.III<br />

1,200 MW power plant at Sidhi, State of Madhya Pradesh<br />

1. Implementation Agreement dated May 27, 2008 and amended on October 26, 2009 between our<br />

Company and the Governor of Madhya Pradesh (“M.P. Government”) for 1200 MW coal based<br />

thermal power project in the State of Madhya Pradesh<br />

Our Company and the M.P. Government entered into an implementation agreement dated May 27, 2008<br />

(“IA”) for the implementation of coal based thermal power project having installed capacity of 1200 MW to be<br />

established at village Musamudi and Bhumka, district Sidhi, State of Madhya Pradesh, India (“Sidhi<br />

Project”). The IA replaces the memorandum of understanding, dated January 16, 2007 which was amended on<br />

December 26, 2007, between our Company and the M.P. Government for setting up of the Project.<br />

As per the IA, our Company is to provide, on an annualized basis to the M.P. Government, five (5) percent of<br />

the net power generated by the Sidhi Project at variable charges determined by the appropriate commission. In<br />

the event our Company is also allocated captive coal block in the State of Madhya Pradesh for supply of coal<br />

to the Sidhi Project, then our Company will provide, on an annualized basis, to the M.P. Government seven<br />

and a half (7.5) percent of the net power generated by the Sidhi Project at variable charges determined by the<br />

appropriate commission. While the M.P. Government does not guarantee the purchase of power from our<br />

Company except for the power mentioned above, the M.P. Government or its nominated agency shall have the<br />

first right of refusal to purchase power up to thirty percent of the aggregate capacity of the generating units for<br />

a period of twenty (20) years through its nominated agency, at the rate to be approved by the appropriate<br />

commission. Our Company is required to enter into a separate wheeling agreement to transfer power to its<br />

consumers or licensee in accordance with the provisions of the Electricity Act, 2003 and in accordance with<br />

applicable regulations either through MP Power Transmission Company Limited or PGCIL/other grid lines or<br />

its own dedicated lines as the conditions necessitate and as may be technically feasible. Our Company shall<br />

achieve the commercial date of operation within sixty (60) months from the date of the IA.<br />

Our Company is permitted to incorporate a public/private limited company for the implementation of the<br />

Project with its registered office within the State of Madhya Pradesh. All rights and obligations under the IA<br />

shall thereafter be transferred to the new company. Unless otherwise permitted by the Government, the<br />

aggregate equity contribution of our Company shall not be less than fifty one (51) per cent during the<br />

construction period and until two years following the commencement of commercial operations. Accordingly,<br />

an amendment agreement was executed on October 26, 2009 to amend the IA to, among other things, to form a<br />

376

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!