7<br />
7) Delivery Period:-<br />
The total period for supply shall be 60 days after receipt of chassis. Detailed dimensional drawings<br />
with bill of material for each type of equipment & CPM/PERT Chart shall be submitted to MCJ in<br />
triplicate for approval within 15 days of receipt of order. The equipment shall have to be delivered<br />
at JALLANDHAR Municipal Corporation<br />
8) Indemnity bond :<br />
Successful bidder has to submit indemnity bond against the cost of truck chassis before receiving<br />
from authorized dealer, which will remain valid till delivery of goods at MCJ site .<br />
9) Delay in performance:-<br />
Delivery of the goods and performance of service shall be made by supplier in accordance with the<br />
schedule specified in the specification.<br />
An unexcused delay by the supplier in the performance of its delivery obligations shall<br />
under the supplier liable to forfeited of its performance security, imposition of liquidated damages<br />
and/or termination of the contract by default. If the supplier fails to deliver any or all of the goods<br />
or fail to perform to services within the said period, the corporation shall deduct from the contract<br />
price as liquidated damages, a sum equivalent to 0.5 percent of the delivered price, of the delayed<br />
goods per week upto maximum of 10% of delayed goods value.<br />
S.E.(O & M)<br />
Municipal Corp. Jalandhar<br />
Bidder’s Signature<br />