• In extreme circumstances, if the tendering agency requires an extension of the time limit for<br />

completion of the work due to unavoidable circumstances, it shall apply in writing to the<br />

Superintending Engineer, well before the expiry of the time limits. Decision of Commissioner,<br />

MCJ shall be final and binding.<br />

5.7 Schedule of Payment**<br />

After initial payments of 5% against mobilization and first report, payments shall be<br />

released only after field verification of property attributes by MCJ using a Monitoring<br />

Mechanism. Under this, MCJ shall devise a system of random verification of attributes of<br />

properties before payment. If during verification, 2% of total attributes of properties (if MCJ<br />

rechecks 50 properties with 30 attributes, it shall be considered as 1500 attributes. i.e. an<br />

error in only 30 attributes) are not correct, the bidder shall not be paid, shall have to carry<br />

out the survey once again and the charges of verification shall have to be borne by the<br />

bidder/contractor (deducted from their bills). During attribute verification of plot/covered area<br />

dimensions i.e length, width etc. an error of ± 5% shall be considered satisfactory. However,<br />

the monitoring criteria could be relaxed by MCJ, if in the views of MCJ, the field feedback is<br />

different than MCJ’s expectations and there are enough justifications to relax it. Decision of<br />

Commissioner MCJ shall be final.<br />

Payments shall be effected as follows:<br />

1. 5% payment on finalization of detailed survey formats, development of Unique property<br />

ID system, database formats and on mobilization of key personnel and required<br />

equipment and initiation of field survey<br />

2. 25% payment on submission of database of about 40% of estimated properties and<br />

validation of 20% of estimated properties<br />

3. 25% payment on submission of database of a total of 75% of estimated properties and<br />

validation of 50% properties.<br />

4. 30% on submission of database preparation of about 100% of estimated properties<br />

including its meeting monitoring requirements (not more than 2% property attribute<br />

should be incorrect) including preparation of maps & validation of 100% properties.<br />

5. 10% on successful demonstration of GIS enabled database system and its handing over<br />

to MCJ (compete in all respects)<br />

6. 5% payment on final acceptance of deliverables - completion of all survey and database<br />

works and their submission in required formats along with training of MCJ staff and<br />

successful operation by MCJ staff. After completion of one successful cycle of billings as<br />

per new database.<br />

7. Release of EMD within 45 days of final payment and on rectification of any observed<br />

faults by MCJ during its operation by them.<br />

- 27 -