the reimbursement <strong>in</strong> full or <strong>in</strong> part as the case may be, shall be met, at the<br />
option of the purchaser from out of all or any of the follow<strong>in</strong>g sources viz:<br />
i) Any amount due and payable to the contractor by the purchaser on any account<br />
whatsoever;<br />
ii)<br />
The Contractor's security deposit <strong>in</strong> hands of the purchaser as far as available<br />
and any other assets whatsoever of the contractor;<br />
In the event of re-imbursement from out of sources (i) and/or (ii) above<br />
mentioned, the purchaser shall have the right of appropriation suo-moto.<br />
35. LIQUIDATED DAMAGES AND TOKEN PENALTY :<br />
35.1 If the contractor fails to execute and complete the work with<strong>in</strong> the time<br />
specified <strong>in</strong> the Agreement or with<strong>in</strong> the period of extension granted except <strong>in</strong><br />
so far as the delay is on the purchaser’s account, the contractor shall be levied<br />
Liquidated Damages at the rate of 1/2% per week or part thereof the entire<br />
contract value of the work awarded to the contractor for delays <strong>in</strong> supply /<br />
execution of the work as per General Conditions of Contract, 1969 for the<br />
North Central Railway Eng<strong>in</strong>eer<strong>in</strong>g department with up to date modifications.<br />
For the purpose of this clause, the contract value of the works shall be taken as<br />
value of work as per contract agreement <strong>in</strong>clud<strong>in</strong>g any supplementary work<br />
order/contract agreement issued. Provided also, that the total amount of<br />
liquidated damages under this condition, shall not exceed the under noted<br />
percentage value or of the total value of the item or groups of items of work<br />
for which a separate dist<strong>in</strong>ct completion period is specified <strong>in</strong> the contract.<br />
(i) For contract value up to Rs.2 lakh – 10% of the total value of the contract.<br />
(ii) For contracts valued above Rs.2 lakh –10% of the first Rs.2<br />
lakh and the 5% of the balance.<br />
Provided further, that if the Railway is not satisfied that the works can be<br />
completed by the Contractor and <strong>in</strong> the event of failure on the part of the<br />
contractor to complete the work with<strong>in</strong> further extension of time allowed as<br />
aforesaid, the Railway shall be entitled, without prejudice to any other right or<br />
remedy available <strong>in</strong> that behalf, to appropriate the contractor’s security<br />
deposit and resc<strong>in</strong>d the contract under clause 62 of these conditions, whether<br />
or not actual damage is caused by such default.<br />
35.2 If such a failure as aforesaid shall have arisen from any cause which the<br />
Purchaser may agree as be<strong>in</strong>g a reasonable ground for extension of time, the<br />
railway may allow such additional time as it may <strong>in</strong> its absolute discretion<br />
consider to be reasonably justified by the circumstances of the case. The<br />
contractor will apply for extension at least one month before the expiry of the<br />
period of completion. In case extension is on Purchaser’s account and also <strong>in</strong><br />