Special Conditions of Contract 1. TENDER DOCUMENTS 2. AGREEMENT 3. SECURITY DEPOSIT & CONTRACT PERFORMANCE GUARANTEE 4. CONTRACTOR'S OFFICE & STORES DEPOT 5. USE OF RAILWAY LAND 6. PROGRAMME OF WORK/OBLIGATION TO CARRY OUT ENGINEER’S INSTRUCTIONS 7. COMPETENT SUPERVISORS 8. MATERIAL SUPPLIED BY RAILWAYS 9. MATERIAL SUPPLIED BY CONTRACTOR 10. OTHER RAILWAY STORES: 11. TESTING & MEASURING INSTRUMENTS, SPECIAL TOOLS AND INSTALLATION MATERIAL 12. SUPPLY OF TECHNICAL LITERATURES, DOCUMENTATION, DRAWINGS & COMPLETION PLANS ETC. 13. SPARES 14. LONG TERM AVAILABILITY OF SPARES AND SYSTEM SUPPORT 15. QUALITY ASSURANCE 16. EQUIPMENT EVALUATION AND APPROVAL 17. INSPECTION OF MATERIALS 18. INSPECTION OF WORKS 19. QUANTUM OF WORK AND VARIATION IN QUANTITIES Signature of contractor Page 48 of 104 Dy CSTE/Proj/IRPMU/CNB

20. ADDITION/REDUCTION OF WORK 21. SUBLETTING AND ASSIGNMENT 22. EXECUTION OF WORK 23. PROGRESS REPORTING 24. MAINTENANCE OF WORKS 25 CLEARANCE OF SITE 26. PROVISIONAL ACCEPTANCE 27. PLACING IN SERVICE & MAINTENANCE SUPERVISION 28 FINAL ACCEPTANCE 29. WARRANTY 30. TRAINING 31. INFRINGEMENT OF PATENTS 32. LICENSE AS PER GOVT. OF INDIA CONTRACT LABOUR ACT 33. DEFAULT & DELAYS 34. LOSS SUSTAINED DUE TO DEFAULT AND DELAY 35. PENALTY FOR DELAY IN COMPLETION 36. EXTENSION OF TIME 37. CONTRATOR'S LIABILITIES FOR COSTS AND DAMAGES 38. UNIT PRICES 39. MEASUREMENT OF WORKS 40. TERMS OF PAYMENT 41. ON ACCOUNT PAYMENT Signature of contractor Page 49 of 104 Dy CSTE/Proj/IRPMU/CNB

Special Conditions of Contract<br />

1. TENDER DOCUMENTS<br />

2. AGREEMENT<br />

3. SECURITY DEPOSIT & CONTRACT PERFORMANCE GUARANTEE<br />

4. CONTRACTOR'S OFFICE & STORES DEPOT<br />

5. USE OF RAILWAY LAND<br />

6. PROGRAMME OF WORK/OBLIGATION TO CARRY OUT ENGINEER’S<br />

INSTRUCTIONS<br />

7. COMPETENT SUPERVISORS<br />

8. MATERIAL SUPPLIED BY RAILWAYS<br />

9. MATERIAL SUPPLIED BY CONTRACTOR<br />

10. OTHER RAILWAY STORES:<br />

11. TESTING & MEASURING INSTRUMENTS, SPECIAL TOOLS AND<br />

INSTALLATION MATERIAL<br />

12. SUPPLY OF TECHNICAL LITERATURES, DOCUMENTATION,<br />

DRAWINGS & COMPLETION PLANS ETC.<br />

13. SPARES<br />

14. LONG TERM AVAILABILITY OF SPARES AND SYSTEM SUPPORT<br />

15. QUALITY ASSURANCE<br />

16. EQUIPMENT EVALUATION AND APPROVAL<br />

17. INSPECTION OF MATERIALS<br />

18. INSPECTION OF WORKS<br />

19. QUANTUM OF WORK AND VARIATION IN QUANTITIES<br />

Signature of contractor Page 48 of 104 Dy CSTE/Proj/IRPMU/CNB