Document - irpmu.railnet.gov.in
Document - irpmu.railnet.gov.in Document - irpmu.railnet.gov.in
7 Installation and complete wiring of indication operating panel. This includes complete supply and provision of indoor cable and wires of 1x1mm, 1x0.6, 3/0.737mm,16/0.20mm flexible 40x0.6mm, 40x1mm, 60x0.6mm, 60x1mm dia cu conductor as confirming to latest IRS specification, IRSEM provision and instructions of engg at site .this includes provision of panel tag blocks, wiring from panel tag blocks to relay racks, CT rack in the relay room including provision of terminal in the panel and termination in the panel. fused bulbs/LEDs shall be replace during testing period 10% of the bulbs /buttons, LEDs of each colour shall be given as spare after commissioning. Installation will also include minute civil works. Cable from panel to relay rack will be taken in GI pipe under ground for which masonry work if required will be done by contractor. Note: wherever panel/indication room and relay room are at a distance and outdoor underground signalling cable is to be laid outdoor sig cable will be supplied by railways and the work of trenching and laying etc shall be covered separately under the item of cable trenching and laying etc Nos. 2 3229.49 6458.98 Consignee. 8 Design and preparation of existing circuit diagram with PI/SSI/Cabin installations to suit alteration for automatic block working .( for small station). Alteration in design & drawings to be done for one side auto section and supplied. 9 Design and Supply of Existing Station SSI Software to suit alteration for Automatic block working. This includes software for Indication panel, Executive software Application logic and all Interconnecting Cables. Alteration in design to be done for one side auto section and made FAT and supplied. 10 Alteration work in operating cum indication Domino panel to include automatic block territory .This includes supply of additional dominos and cover plates along with LEDs, Cables and wiring etc. Alteration in design to be done for one side auto section and supplied. job 2 82500 165000 Consignee job 1 181500 181500 Consignee job 2 13200 26400 Consignee Total 19675118.98 Tenderer to Quote % above/Below on above Schedule Rates Note: At any SSI station if automatic signalling work is carried out in one side only than payment for the alteration work in circuit, SSI & VDU and operating cum indication Domino panel will be done as per Sr. No.8,9 & 10 respectively. Similarly if at any station automatic signalling testing of alterations and commissioning is in one side only than payment for these activities will be made 50% of item no 5 and 6 respectively. Signature of contractor Page 26 of 104 Dy CSTE/Proj/IRPMU/CNB
SCHEDULE –C Schedule for Supply of SSI matrial. S.No. Description of Item Unit Qty. Rates Total Inspection 1 MLK-II Card Files Nos. 4 156,498.44 625993.76 RDSO 2 MLK - II CPU PCBs Nos. 4 169,567.05 678268.20 RDSO 3 MLK - II PS PCBs Nos. 4 90,032.51 360130.04 RDSO 4 MLK - II Vital Input PCB Nos. 50 65,463.05 3273152.50 RDSO 5 MLK - II O/P PCB Nos. 120 59,562.93 7147551.60 RDSO 6 MLK - II Non - Vital I / O PCB Nos. 140 74,995.89 10499424.60 RDSO 7 VCOR Relay Nos. 4 89,016.22 356064.88 RDSO 8 VCOR Relay Base Nos. 4 6,837.37 27349.48 RDSO 9 Address Select PCB - 48 Pin Nos. 10 5,389.66 53896.60 Consignee 10 Address Select PCB - 96 Pin Nos. 10 6,764.12 67641.20 Consignee 11 CPU EEPROM PCB Nos. 8 6,006.64 48053.12 Consignee 12 1 Wide Blank front panel Nos. 24 2,373.01 56952.24 Consignee 13 PCB Keying plug. Nos. 50 27.00 1350.00 Consignee 14 48 Pin Connector Housing Assy Nos. 80 1,322.50 105800.00 Consignee 15 48 Pin Connector Guide Element Nos. 80 642.03 51362.40 Consignee 16 96 Pin Connector Housing Assy Nos. 20 1,235.88 24717.60 Consignee 17 96 Pin Connector Guide Element Nos. 20 619.16 12383.20 Consignee 18 48 Pin Female Connector Nos. 20 302.08 6041.60 Consignee 19 48 Pin Female Crimp contact Nos. 3000 31.81 95430.00 Consignee 20 96 Pin Female Connector Nos. 10 516.91 5169.10 Consignee 21 96 Pin Female Crimp contact. Nos. 2000 20.71 41420.00 Consignee 22 UPS for computer Nos. 2 12,447.24 24894.48 Consignee 23 Sync PCB. (MDSC) Nos. 4 135,975.00 543900.00 RDSO 24 COMMS PCB Nos. 4 130,000.00 520000.00 RDSO 25 230 V Lightning Arrestors Nos. 4 12,607.89 50431.56 Consignee 26 12V Lightning Arrestors Nos. 4 12,929.00 51716.00 Consignee 27 24 V Lightning Arrestors. Nos. 4 12,882.00 51528.00 Consignee 28 Isolators Nos. 4 8,926.33 35705.32 Consignee 29 DC-DC Convertors Microlock. Nos. 10 21,565.93 215659.30 Consignee 30 Microlok Rack with accessories Nos. 2 75,553.63 151107.26 Consignee 31 Relay Rack with Accessories Nos. 2 25,863.30 51726.60 Consignee 32 Termination Rack Nos. 1 16,383.71 16383.71 Consignee 33 Industrial grade computer with 42" Industrial Nos. 2 311,904.00 623808.00 Consignee Grade VDU for use as Maintenance Console & Operator Console. 34 Laser Jet printer. Nos. 2 18,905.87 37811.74 Consignee 35 Consumable manufacturing such as indoor connecting to the extent of alterations in EI LOT 30 20,250.15 607504.50 Consignee Signature of contractor Page 27 of 104 Dy CSTE/Proj/IRPMU/CNB
- Page 1 and 2: IRPMU INDIAN RAILWAYS PROJECT MANAG
- Page 3 and 4: INDEX SECTION CHAPTER SUBJECT I 1 T
- Page 5 and 6: INDIAN RAILWAY PROJECT MANAGEMENT U
- Page 7 and 8: PREAMBLE 1 Tender Notice No. IRPMU/
- Page 9 and 10: j. The Earth enhancement material s
- Page 11 and 12: B) Typical bonding and Earthing con
- Page 13 and 14: 2.3.2 Sch. B Design Modification of
- Page 15 and 16: assembly, guide element, female con
- Page 17 and 18: Wiring in relays housing shall be u
- Page 19 and 20: 4.3 a) The tenderer(s) should submi
- Page 21 and 22: these originally quoted for, based
- Page 23 and 24: Section - I Chapter - 3 Schedule of
- Page 25: Schedule -B Schedule for Alteration
- Page 29 and 30: Section - II Chapter - 1 Instructio
- Page 31 and 32: 23. AUTHORITY FOR ACCEPTANCE 24. PU
- Page 33 and 34: "CONTRACTOR” Means the successful
- Page 35 and 36: change of price, or time schedule o
- Page 37 and 38: within reasonable time after the fi
- Page 39 and 40: 7.1 Any individual(s) signing the t
- Page 41 and 42: entertained. 16. WRONG INFORMATION
- Page 43 and 44: 18.2.3 COMPLETION PERIOD OF WORK Th
- Page 45 and 46: derived from the multiplication of
- Page 47 and 48: Section - II Chapter - 2 Special Co
- Page 49 and 50: 20. ADDITION/REDUCTION OF WORK 21.
- Page 51 and 52: SPECIAL CONDITIONS OF CONTRACT 1. T
- Page 53 and 54: irrevocable bank Guarantee (issued
- Page 55 and 56: 6.6 No facility whatsoever, e.g. pr
- Page 57 and 58: 9 MATERIAL SUPPLIED BY CONTRACTOR 9
- Page 59 and 60: 15.1 The tenderer shall certify tha
- Page 61 and 62: and cost of the contractor. In the
- Page 63 and 64: During inspection of installation b
- Page 65 and 66: All the work shall be executed in s
- Page 67 and 68: approved test procedure have been c
- Page 69 and 70: 29.3 During the period of Warranty,
- Page 71 and 72: the reimbursement in full or in par
- Page 73 and 74: If such a failure as aforesaid shal
- Page 75 and 76: Banker's charges for guarantees, co
7 Installation and complete wir<strong>in</strong>g of <strong>in</strong>dication operat<strong>in</strong>g<br />
panel. This <strong>in</strong>cludes complete supply and provision of<br />
<strong>in</strong>door cable and wires of 1x1mm, 1x0.6,<br />
3/0.737mm,16/0.20mm flexible 40x0.6mm, 40x1mm,<br />
60x0.6mm, 60x1mm dia cu conductor as confirm<strong>in</strong>g to<br />
latest IRS specification, IRSEM provision and <strong>in</strong>structions<br />
of engg at site .this <strong>in</strong>cludes provision of panel tag blocks,<br />
wir<strong>in</strong>g from panel tag blocks to relay racks, CT rack <strong>in</strong> the<br />
relay room <strong>in</strong>clud<strong>in</strong>g provision of term<strong>in</strong>al <strong>in</strong> the panel and<br />
term<strong>in</strong>ation <strong>in</strong> the panel. fused bulbs/LEDs shall be replace<br />
dur<strong>in</strong>g test<strong>in</strong>g period 10% of the bulbs /buttons, LEDs of<br />
each colour shall be given as spare after commission<strong>in</strong>g.<br />
Installation will also <strong>in</strong>clude m<strong>in</strong>ute civil works. Cable from<br />
panel to relay rack will be taken <strong>in</strong> GI pipe under ground for<br />
which masonry work if required will be done by contractor.<br />
Note: wherever panel/<strong>in</strong>dication room and relay room are<br />
at a distance and outdoor underground signall<strong>in</strong>g cable is<br />
to be laid outdoor sig cable will be supplied by railways and<br />
the work of trench<strong>in</strong>g and lay<strong>in</strong>g etc shall be covered<br />
separately under the item of cable trench<strong>in</strong>g and lay<strong>in</strong>g etc<br />
Nos. 2 3229.49 6458.98 Consignee.<br />
8 Design and preparation of exist<strong>in</strong>g circuit diagram with<br />
PI/SSI/Cab<strong>in</strong> <strong>in</strong>stallations to suit alteration for automatic<br />
block work<strong>in</strong>g .( for small station). Alteration <strong>in</strong> design &<br />
draw<strong>in</strong>gs to be done for one side auto section and<br />
supplied.<br />
9 Design and Supply of Exist<strong>in</strong>g Station SSI Software to suit<br />
alteration for Automatic block work<strong>in</strong>g. This <strong>in</strong>cludes<br />
software for Indication panel, Executive software<br />
Application logic and all Interconnect<strong>in</strong>g Cables. Alteration<br />
<strong>in</strong> design to be done for one side auto section and made<br />
FAT and supplied.<br />
10 Alteration work <strong>in</strong> operat<strong>in</strong>g cum <strong>in</strong>dication Dom<strong>in</strong>o panel<br />
to <strong>in</strong>clude automatic block territory .This <strong>in</strong>cludes supply of<br />
additional dom<strong>in</strong>os and cover plates along with LEDs,<br />
Cables and wir<strong>in</strong>g etc. Alteration <strong>in</strong> design to be done for<br />
one side auto section and supplied.<br />
job 2 82500 165000 Consignee<br />
job 1 181500 181500 Consignee<br />
job 2 13200 26400 Consignee<br />
Total 19675118.98<br />
Tenderer to Quote % above/Below on above Schedule Rates<br />
Note: At any SSI station if automatic signall<strong>in</strong>g work is carried out <strong>in</strong> one side only than payment for the<br />
alteration work <strong>in</strong> circuit, SSI & VDU and operat<strong>in</strong>g cum <strong>in</strong>dication Dom<strong>in</strong>o panel will be done as per Sr.<br />
No.8,9 & 10 respectively. Similarly if at any station automatic signall<strong>in</strong>g test<strong>in</strong>g of alterations and<br />
commission<strong>in</strong>g is <strong>in</strong> one side only than payment for these activities will be made 50% of item no 5 and 6<br />
respectively.<br />
Signature of contractor Page 26 of 104 Dy CSTE/Proj/IRPMU/CNB