5. The adjustment for variation <strong>in</strong> prices if required shall be made once every quarter<br />

<strong>in</strong> the on account payments. If more than one on-account payment is made to<br />

the contractor <strong>in</strong> a quarter the adjustment, if required, shall be made <strong>in</strong> each bill.<br />

6. Price variation dur<strong>in</strong>g extended period of contract:<br />

The price adjustment as worked out above i.e. either <strong>in</strong> crease or decrease will<br />

be applicable up to the stipulated date of completion of the work <strong>in</strong>clud<strong>in</strong>g the<br />

extended period of completion where such extension has been granted under<br />

Clause 17(1), 17(2) & 17(3) of the General Conditions of Contract. However,<br />

where extensions of time has been granted due to contractor's failure under<br />

Clause 17(4) of the General Conditions of Contract. Price adjustment will be<br />

done as follows:-<br />

(a) In case the <strong>in</strong>dices <strong>in</strong>crease above the <strong>in</strong>dices applicable to the last month<br />

or orig<strong>in</strong>al completion period or the extended period under Clause 17(1),<br />

17(2) or 17(3) the price adjustment of the period of extension granted<br />

under Clause 17(4) will be limited to the amount payable as per the<br />

<strong>in</strong>dices applicable to the last month of the orig<strong>in</strong>al completion period of the<br />

extended period under Clause 17(1), 17(2) or 17(3) of General Conditions<br />

of Contract, as the case may be.<br />

(b)<br />

In case the <strong>in</strong>dices fall below the <strong>in</strong>dices applicable to the last month of the<br />

orig<strong>in</strong>al/extended period of completion under Clause 17(1), 17(2) or 17(3),<br />

as the case may be then the lower <strong>in</strong>dices will be adopted for price<br />

adjustment for the period of extension under Clause 17 (4) of the<br />

General Conditions of Con tract.<br />

7. Applicability and ceil<strong>in</strong>g limit for Price Variation shall be as follows:<br />

(a)<br />

Price Variation Clause (PVC) shall be applicable for tenders of value more<br />

than Rs 50 Lakh irrespective of the contract completion period and PVC<br />

shall not be applicable to tenders of value less than Rs 50 lakh.<br />

NOTE:<br />

(1) Materials supplied free by the Railway to the contractors will not form part<br />

of the value of the contract entered <strong>in</strong>to and will fall outside the purview of<br />

the price variation clause.<br />

(2) Duration of the contract shall be prescribed <strong>in</strong> the tender documents at the<br />

time of <strong>in</strong>vit<strong>in</strong>g tenders and will not <strong>in</strong>clude the extended period due to<br />

extension, if any, given".<br />

33.0 MACHINERY AND PLANT:<br />

33.1 The contractor will be entirely responsible to arrange all necessary mach<strong>in</strong>ery, i.e<br />

rig mach<strong>in</strong>e, concrete mixers, vibrators, compressors, pumps, pneumatic<br />

equipment’s, dredges, derricks, cranes, service girders, stag<strong>in</strong>g, motor-vehicle,<br />