31.0 Labour:<br />
31.1 The pr<strong>in</strong>cipal Contractor/s will be held responsible for the compliance with<br />
provision of Wages Act 1936 and Rules framed there under even <strong>in</strong> respect of<br />
labour employed <strong>in</strong> his/their sub contractor <strong>in</strong> the execution of the work<br />
contracted by him/them.<br />
31.2 The contractor/s shall carry out the provision of any regulation that may be<br />
enforced <strong>in</strong> the area <strong>in</strong> which work is to be done prohibit<strong>in</strong>g the recruitment of<br />
local labour.<br />
31.3 The contractor/s shall obta<strong>in</strong> license from the appropriate licens<strong>in</strong>g officer of the<br />
area before commencement of the work and shall produce a copy there of along<br />
with the orig<strong>in</strong>al to the Dy. CE/IRPMU to start the work.<br />
31.4.1 In any case <strong>in</strong> which by virtue of relevant sections of the Contract Labour<br />
(Regulation and Abolition) Act 1970, the Railway is obliged to provide amenities<br />
and or pay wages to labour employed by the contractor or through petty<br />
contractor or sub contractor/s under this contract, then the contractor shall<br />
<strong>in</strong>demnify the Railway fully and Railway shall be entitled to recover from the<br />
contractor the expenditure <strong>in</strong>curred on provid<strong>in</strong>g the said amenities and or wages<br />
so paid by deduct<strong>in</strong>g it from the security deposit or from any sum due to the<br />
contractor (from the Railway) provided that if any dispute arises as to the<br />
expenditure <strong>in</strong>curred by the Railway or provisions of the said amenities, the<br />
decision of the Eng<strong>in</strong>eer shall be f<strong>in</strong>al and b<strong>in</strong>d<strong>in</strong>g.<br />
31.4.2 The Contractor/s shall provide Rest Shelters, Latr<strong>in</strong>es and Ur<strong>in</strong>als, Wash<strong>in</strong>g<br />
facilities, First aid and Medical facilities strictly <strong>in</strong> accordance with the provision of<br />
relevant sections of Contractor Labour Central Rules-1989. If the contractor does<br />
not provide these facilities, with<strong>in</strong> the stipulated periods, the Railway will provide<br />
these and the cost of the same will be recovered from the contractor/s.<br />
31.5 The Railway will not take responsibility or make arrangements for Supply of Food<br />
Stuff to the contractor/s his/their staff or labourers.<br />
31.6 The contractor shall make his/their own arrangement at his/their own cost for<br />
supply of water to his/their staff and labour and the Railway under take no<br />
responsibility for supply of water to the contractor/s his/their staff or labour or for<br />
the work.<br />
31.7 The contractor shall take all precautionary measures <strong>in</strong> order to ensure<br />
protection of their own personal mov<strong>in</strong>g about or work<strong>in</strong>g on the Railway<br />
premises and shall have to conform to the Rules and Regulation of the North<br />
Central Railway. If unforeseen accident or <strong>in</strong>jury happens while on work<strong>in</strong>g the<br />
contractor shall be solely responsible for the same.<br />