supply arrangements. On request by the contractor the Dy. Chief<br />

Eng<strong>in</strong>eer/IRPMU., may give assistance only to the extent of recommend<strong>in</strong>g the<br />

contractor’s application for water supply to any authority for arrang<strong>in</strong>g such<br />

supply.<br />

12.0 INTERUPTION OF WORKS DURING MONSOONS:-<br />

The contract period will extend over a monsoon. The contractor should therefore,<br />

plan and prepare his work keep<strong>in</strong>g this fact <strong>in</strong> m<strong>in</strong>d.<br />

13.0 PATENTED DEVICES MATERIALS AND PROCESSES:-<br />

When the contractor desires to use any designed device, material or process<br />

covered by a letter of patent or copy right, the right for such use shall be secured<br />

by suitable legal arrangement and agreement with patent owner and copy of the<br />

agreement shall be filed with Railways if so required. The contractor shall also<br />

<strong>in</strong>demnify railways aga<strong>in</strong>st any claims aris<strong>in</strong>g out of above.<br />

14.0 MAINTENANCE PERIOD:-<br />

14.1 The ma<strong>in</strong>tenance period of the permanent works shall be treated as 06 (six)<br />

months from the date of completion.<br />

14.2 No part refund of security deposit shall be permitted dur<strong>in</strong>g the ma<strong>in</strong>tenance<br />

period.<br />

15.0 SETTING OUT OF WORKS<br />

15.1 The contractor is to set out the whole of the work <strong>in</strong> consultation with an official to<br />

be deputed by the Eng<strong>in</strong>eer <strong>in</strong> charge and dur<strong>in</strong>g progress of the work to amend<br />

on the requisition of the Eng<strong>in</strong>eer, any error which may arise their <strong>in</strong> and provide<br />

efficient and sufficient staff and labour thereof. The contractor shall also amend or<br />

alter any error <strong>in</strong> the dimensions, l<strong>in</strong>es or levels to the satisfaction of the Eng<strong>in</strong>eer<br />

<strong>in</strong> charge or his authorised representative without claim<strong>in</strong>g any compensation for<br />

the same.<br />

15.2 The contractor at his own cost shall provide pegs and be responsible for the<br />

ma<strong>in</strong>tenance of all stakes, templates, profiles, land mark, po<strong>in</strong>ts, burgees,<br />

monuments, centre l<strong>in</strong>e pillars, reference pillars etc. and shall take all precautions<br />

to prevent these be<strong>in</strong>g removed, altered or disturbed and will be responsible for<br />

the consequences of such removals, alterations, or disturbance and for their<br />

efficient re<strong>in</strong>statement.<br />

16.0 LAY OUT:<br />

16.1 Alignment and layout pillars as may be considered necessary by the Eng<strong>in</strong>eer-<strong>in</strong>charge<br />

up to formation level beh<strong>in</strong>d each of the bridge abutments should be<br />

constructed by the contractor at his own cost to de-note centre l<strong>in</strong>e. These shall<br />