Tender Document - irpmu.railnet.gov.in

Tender Document - irpmu.railnet.gov.in Tender Document - irpmu.railnet.gov.in

irpmu.railnet.gov.in
from irpmu.railnet.gov.in More from this publisher
01.02.2015 Views

8.1 The entire work is required to be completed in all respects within Nine Months from the date of issue of the acceptance letter/telegram. Time is the essence of contract. The contractor/s will be required to maintain speedy and required progress to the satisfactions of the Engineer to ensure that the work will be completed in all respects within the stipulated period failing which action may be taken by the Railway Administration in terms of Clause 17 and/or Clause 62 of the General Conditions of Contract 2005 8.2 The contractor/s shall arrange to execute the different items of works in close consultation with and as per directions of the Engineer so that other works being executed in the same area either departmentally or through another agency such as steel erection, P. Way earthwork in formation, etc. are also progressed concurrently. It may be noted, however, that any delay in the execution of departmental works, for whatsoever reason shall not be accepted as an excuse for non-performance of the contract. 8.3 The contractor/s will be required to give to Dy. Chief Engineer/IRPMU a monthly progress report of the work done during the month on 4 th of the following month. He will also give to the Dy. Chief Engineer the programme of work to be done in coming month by 25 th of the preceding month. The programme will be subject to alteration or modifications at the direction of the Chief Administrative Officer/ IRPMU, Shivaji Bridge, New Delhi who may discuss such modifications or alterations with the contractor as considered necessary. Approval of any programme shall not in any way relieve the contractor from any of his obligations to complete the whole of the work by the prescribed time or extended time, if any. 9.0 RATES FOR PAYMENT 9.1 The rates given in the attached schedule of rates tendered by the contractor and as accepted by the Railways will form the basis of payment for such items under this contract. 9.2 No material price variation or wages escalation on any account whatsoever the compensation for `Force Majure' etc. shall be payable under this contract except price escalation clause payable as per price escalation clause, if any, provided separately in the tender documents. 9.3 The rates for any item of work not included in the (Schedule of Items, Rates and Quantities) and which the contractor may be called upon to do by Railway Administration shall be fixed by the supplementary written agreement between the contractor and the Railway before the particular item or items of work is/are executed. In the event of such agreement not being entered into and executed the Railway may execute these works by making alternative arrangements. Railways will not be responsible for any loss or damages on this account. OS/Works 18

9.3.1 The contractor shall work in close co-operation with the contractors, departmental staff working in the adjacent sections of railway & local authorities. 9.4 It should be specifically noted by the tenderers that no separate loading, unloading and leading charges for materials (which are supplied by the Railway) shall be paid for by the Railways and the rates quoted by the tenderer/s shall be inclusive of all these charges. 9.5 The item Nos., description, units and rates given in schedule of rates are as per North Central Railway Standard Schedule of Rates 2006 and any discrepancy during the execution of the work in the working rates, quantity and units etc. Should be rectified by reference to the printed schedule of rates which be treated as authority and will be binding on the contractor. 9.6 Should there arise any items which may be necessary for the completion of work but which does not appear in the Schedule of Items, Rates and Quantities attached with tenders, its rate will be fixed by analysis of actual inputs of all types including labour and material or derived from the labour and material rates given in the North Central Railway Standard Schedules of Rates 2006. The rates for such non-scheduled items occurring during the course of construction shall be payable subject to the approval of the competent authority. No items or work requiring non-schedule rates will be carried out unless ordered to do so by the Engineer. The rates derived from the North Central Railway Standard Schedules of Rates 2006 will be subject to percentage above or below tendered by the contractor. 9.7 Payment for the work done will be made to the contractor only when the formal agreement has been executed between the parties. 9.8 SUPPLEMENTARY AGREEMENT After the work is completed and taken over by the Railway as per terms and conditions of the contract agreement or otherwise concluded by the parties with mutual consent and full and final payment is made by the Railway to the contractor for work done under the contract the parties shall execute the supplementary agreement annexed here to as Annexure-B. 9.9 Measures to be taken in construction and repairs on roads, embankments, etc. 9.9.1 All borrow pits dug for and in connection with the construction and repairs of buildings, roads, embankments, etc. shall be deep and connected with each other in the formation of a drain directed towards the lowest level and properly sloped for discharge into a river, stream, channel or drain and no person shall OS/Works 19

8.1 The entire work is required to be completed <strong>in</strong> all respects with<strong>in</strong> N<strong>in</strong>e Months<br />

from the date of issue of the acceptance letter/telegram. Time is the essence of<br />

contract. The contractor/s will be required to ma<strong>in</strong>ta<strong>in</strong> speedy and required<br />

progress to the satisfactions of the Eng<strong>in</strong>eer to ensure that the work will be<br />

completed <strong>in</strong> all respects with<strong>in</strong> the stipulated period fail<strong>in</strong>g which action may<br />

be taken by the Railway Adm<strong>in</strong>istration <strong>in</strong> terms of Clause 17 and/or Clause 62<br />

of the General Conditions of Contract 2005<br />

8.2 The contractor/s shall arrange to execute the different items of works <strong>in</strong> close<br />

consultation with and as per directions of the Eng<strong>in</strong>eer so that other works<br />

be<strong>in</strong>g executed <strong>in</strong> the same area either departmentally or through another<br />

agency such as steel erection, P. Way earthwork <strong>in</strong> formation, etc. are also<br />

progressed concurrently. It may be noted, however, that any delay <strong>in</strong> the<br />

execution of departmental works, for whatsoever reason shall not be accepted as<br />

an excuse for non-performance of the contract.<br />

8.3 The contractor/s will be required to give to Dy. Chief Eng<strong>in</strong>eer/IRPMU a monthly<br />

progress report of the work done dur<strong>in</strong>g the month on 4 th of the follow<strong>in</strong>g month.<br />

He will also give to the Dy. Chief Eng<strong>in</strong>eer the programme of work to be done<br />

<strong>in</strong> com<strong>in</strong>g month by 25 th of the preced<strong>in</strong>g month. The programme will be subject<br />

to alteration or modifications at the direction of the Chief Adm<strong>in</strong>istrative Officer/<br />

IRPMU, Shivaji Bridge, New Delhi who may discuss such modifications or<br />

alterations with the contractor as considered necessary. Approval of any<br />

programme shall not <strong>in</strong> any way relieve the contractor from any of his obligations<br />

to complete the whole of the work by the prescribed time or extended time, if any.<br />

9.0 RATES FOR PAYMENT<br />

9.1 The rates given <strong>in</strong> the attached schedule of rates tendered by the contractor and<br />

as accepted by the Railways will form the basis of payment for such items under<br />

this contract.<br />

9.2 No material price variation or wages escalation on any account whatsoever the<br />

compensation for `Force Majure' etc. shall be payable under this contract<br />

except price escalation clause payable as per price escalation clause, if any,<br />

provided separately <strong>in</strong> the tender documents.<br />

9.3 The rates for any item of work not <strong>in</strong>cluded <strong>in</strong> the (Schedule of Items, Rates and<br />

Quantities) and which the contractor may be called upon to do by Railway<br />

Adm<strong>in</strong>istration shall be fixed by the supplementary written agreement between<br />

the contractor and the Railway before the particular item or items of work is/are<br />

executed. In the event of such agreement not be<strong>in</strong>g entered <strong>in</strong>to and executed<br />

the Railway may execute these works by mak<strong>in</strong>g alternative arrangements.<br />

Railways will not be responsible for any loss or damages on this account.<br />

OS/Works 18

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!