Project Process<br />
• 3 Schedules of Work 2 Contract Options<br />
• Schedule I – Pavement Rehab (Contract #1)<br />
• Schedule II – Runway Edge Lighting System Replacement (Contract #1)<br />
• Schedule III – Airfield Drainage Improvements (Contract #2)<br />
• Based on funding available once bids received, award one or both contracts<br />
• Prior to bids, team not optimistic to construct both contracts due to funding<br />
limitations