Runway Pavement Rehab – Construction
Runway Pavement Rehab – Construction • Concrete Mix • “Typical” P-501, increase in airentrainment granted to 3.5% • 650 psi flex strength • Delivered in ready-mix trucks, no batch plant • Initial i thoughts h were up to 4 trucks delivering at a time, actual 2-3 • Actual average was ~ 90-100 cubic yards / hour; • On-site QC trailer & beam breaks
- Page 1 and 2: A Concrete Alternative to Asphalt R
- Page 3 and 4: Airport Location • Airport locate
- Page 6 and 7: Project History • Original CIP id
- Page 8 and 9: Project Process • 3 Schedules of
- Page 10 and 11: Runway Pavement Rehab - Design Crit
- Page 12 and 13: Runway Pavement Rehab - Design Crit
- Page 14: Runway Pavement Rehab - Design Crit
- Page 17 and 18: Runway Pavement Rehab - Design Crit
- Page 19 and 20: Runway Pavement Rehab - Asphalt Rec
- Page 21 and 22: Runway Pavement Rehab - PCC Overlay
- Page 23: Runway Pavement Rehab - PCC Overlay
- Page 26 and 27: Runway Pavement Rehab - Life Cycle
- Page 28 and 29: Runway Pavement Rehab - Constructio
- Page 30 and 31: Runway Pavement Rehab - Constructio
- Page 32 and 33: Runway Pavement Rehab - Constructio
- Page 34 and 35: Runway Pavement Rehab - Constructio
- Page 38 and 39: Runway Pavement Rehab - Constructio
- Page 40 and 41: Runway Pavement Rehab - Constructio
- Page 42 and 43: Runway Pavement Rehab - Constructio
- Page 44 and 45: Runway Pavement Rehab - Constructio
- Page 46 and 47: Runway Pavement Rehab - Constructio
- Page 48 and 49: Runway Pavement Rehab - Constructio
- Page 50 and 51: Runway Pavement Rehab - Constructio
- Page 52 and 53: Summary • ~ 36,200 square yards o
Runway Pavement Rehab – Construction<br />
• Concrete Mix<br />
• “Typical” P-501, increase in airentrainment<br />
granted to 3.5%<br />
• 650 psi flex strength<br />
• Delivered in ready-mix trucks,<br />
no batch plant<br />
• Initial i thoughts h were up to 4<br />
trucks delivering at a time,<br />
actual 2-3<br />
• Actual average was ~ 90-100<br />
cubic yards / hour;<br />
• On-site QC trailer & beam<br />
breaks