Runway Pavement Rehab – Asphalt Reclamation P-301 Cement Stabilized Reclaimed Base Course 36,260 SY $3.65 $132,349.00 P-301 Portland Cement for Reclaimed Base Course 1,050 TON $110.00 $115,500.00 P-301 Added Coarse Aggregate for Reclaimed Base Course 1,000 TON $44.85 $44,850.00 P-401 Bituminous Surface Course 9,100 TON $110.00 $1,001,000.00 • Bid with cement as separate item • Additional coarse aggregate anticipated for lack of base course in areas • Initial costs of pavement section alone ~ $1.3 million • Initial costs of all paving-related items ~ $1.48 million

Runway Pavement Rehab – PCC Overlay • Limiting Section 4.4” Asphalt, No Base • Design Flex Strength of 685 psi • k-value of 120 pci • Grade Correction (Milling) • Sand “Bond-Breaker”

Runway Pavement Rehab – Asphalt Reclamation<br />

P-301 Cement Stabilized Reclaimed Base Course 36,260 SY $3.65 $132,349.00<br />

P-301 Portland Cement for Reclaimed Base Course 1,050 TON $110.00 $115,500.00<br />

P-301<br />

Added Coarse Aggregate for Reclaimed Base<br />

Course<br />

1,000 TON $44.85 $44,850.00<br />

P-401 Bituminous Surface Course 9,100 TON $110.00 $1,001,000.00<br />

• Bid with cement as separate item<br />

• Additional coarse aggregate anticipated for lack of base course in areas<br />

• Initial costs of pavement section alone ~ $1.3 million<br />

• Initial costs of all paving-related items ~ $1.48 million