I. PRE-ROOFING CONFERENCE<br />

A pre-roofing conference, attended by the owner, archited,<br />

general contractor, deck contractor, mechanical contractor<br />

and the roofing contractor, should be scheduled<br />

well in advance of ordering materials and beginning work.<br />

If a roof bond is required, a representative from the roofing<br />

materials manufacturer should be present. A written<br />

record should be made of the proceedings and should<br />

become a part of the job record. If the roofing contractor<br />

discovers roof problems in his inspection of the roof, a<br />

second, pre-work inspection should be held.<br />

The architect's specifications, roof plans and all roof and<br />

flashing details should be reviewed at the pre-roofing conference.<br />

Any discrepancies between the architect's and<br />

the manufacturer's specifications should be reviewed<br />

and resolved. In the event that certain discrepancies<br />

arise, the manufacturer's representative should be consulted<br />

to resolve the issue. " FM or UL requirements are<br />

included in the specifications, these requirements should<br />

be carefully reviewed. Building code or architectural<br />

directives that are in conflict with these insurance requirements<br />

should be resolved.<br />

The directives listed below should be followed to assure<br />

a successful pre-roofing conference:<br />

. Establish trade-related job schedules, including the installation<br />

of mechanical equipment.<br />

. Establish roof schedules and work methods that will<br />

prevent roof damage.<br />

. Require that all penetrations and walls be in place prior<br />

to inStalling the roof.<br />

. Establish those areas on the job site that will be designated<br />

as work and storage areas.<br />

. Establish weather and working temperature conditions<br />

to which all parties must agree.<br />

. Establish the conditions for which a temporary roof<br />

would be used and who will pay for its cost.<br />