I. PRE-ROOFING CONFERENCE<br />
A pre-roofing conference, attended by the owner, archited,<br />
general contractor, deck contractor, mechanical contractor<br />
and the roofing contractor, should be scheduled<br />
well in advance of ordering materials and beginning work.<br />
If a roof bond is required, a representative from the roofing<br />
materials manufacturer should be present. A written<br />
record should be made of the proceedings and should<br />
become a part of the job record. If the roofing contractor<br />
discovers roof problems in his inspection of the roof, a<br />
second, pre-work inspection should be held.<br />
The architect's specifications, roof plans and all roof and<br />
flashing details should be reviewed at the pre-roofing conference.<br />
Any discrepancies between the architect's and<br />
the manufacturer's specifications should be reviewed<br />
and resolved. In the event that certain discrepancies<br />
arise, the manufacturer's representative should be consulted<br />
to resolve the issue. " FM or UL requirements are<br />
included in the specifications, these requirements should<br />
be carefully reviewed. Building code or architectural<br />
directives that are in conflict with these insurance requirements<br />
should be resolved.<br />
The directives listed below should be followed to assure<br />
a successful pre-roofing conference:<br />
. Establish trade-related job schedules, including the installation<br />
of mechanical equipment.<br />
. Establish roof schedules and work methods that will<br />
prevent roof damage.<br />
. Require that all penetrations and walls be in place prior<br />
to inStalling the roof.<br />
. Establish those areas on the job site that will be designated<br />
as work and storage areas.<br />
. Establish weather and working temperature conditions<br />
to which all parties must agree.<br />
. Establish the conditions for which a temporary roof<br />
would be used and who will pay for its cost.<br />