The M2 Document Center site is designed to provide a unified approach to saving Measure M<br />
project and program files. Staff training was completed this quarter and the document center<br />
is up and running. Recommendations from users on minor adjustments to the center are<br />
under way and should be in place during the month of October.<br />
Documents in the M drive (the previous system for saving M documents) have been<br />
transferred to the document center and are currently being categorized by staff. The plan is to<br />
have all 1,128 of the files permanently stored with the appropriate identifying metadata in the<br />
document center by the end of the year.<br />
Staff meets quarterly to review all labor costs to ensure proper cost allocation to both M1 and<br />
M2. As a result of this review, the allocation methodology has been updated to more<br />
accurately reflect actual time spent on both M1 and M2 administrative activities. As M1<br />
continues to wind down, staff will look at other refinements that should be incorporated into<br />
the cost allocation plan for FY 2012-13.<br />
During the next quarter, staff will redesign the quarterly report to include a section measuring<br />
progress on the M2020 Plan. Staff will continue to work with CH2M Hill on the performance<br />
assessment and complete the migration of documents from the M drive to the M2 Document<br />
Center.