11. DRILLING<br />

Since 1977, diam<strong>on</strong>d drilling has been carried out intermittently by various operators over five<br />

separate mineralized z<strong>on</strong>es at Thor Lake. A total of 51 holes (5,648 m) had been completed <strong>on</strong><br />

<strong>the</strong> Nechalacho <strong>deposit</strong> through to 1988 (see secti<strong>on</strong> <strong>on</strong> History). As <strong>the</strong> geology was poorly<br />

understood, <strong>the</strong> drilling frequently did not penetrate <strong>the</strong> Basal Z<strong>on</strong>e, and <strong>the</strong> results are often<br />

not useful for <strong>the</strong> present resource model. Also, as noted elsewhere, modern QA/QC practices<br />

were not followed and samples were <strong>on</strong>ly analyzed for <strong>on</strong>ly four to six elements. Modern cheap<br />

and reliable multi element analytical methods were not available. C<strong>on</strong>sequently <strong>the</strong> historic<br />

drilling, in general, is not so useful for <strong>the</strong> resource estimati<strong>on</strong>.<br />

RECENT DRILLING<br />

Aval<strong>on</strong> commenced diam<strong>on</strong>d drilling in <strong>the</strong> Nechalacho <strong>deposit</strong> in July 2007. Drilling was<br />

organized into seven separate drill programs:<br />

• July to October 2007: 13 holes totaling 2,550 m (BTW diameter)<br />

• January to May 2008: 45 holes totaling 8,725 m, including 11 metallurgical holes totaling<br />

2,278 m (NQ2 diameter)<br />

• June to September 2008: 27 holes totaling 5,565 m (NQ2 diameter)<br />

• February to May 2009: 26 holes totaling 5,474 metres (NQ2 diameter)<br />

• July to October 2009: 44 holes totaling 9,098 metres (HQ diameter)<br />

• January to April 2010: 33 holes totaling 7,970 metres (HQ diameter)<br />

• January to April 2010: 10 holes for 11,512 metres (HQ diameter)<br />

• July to October 2010: 41 holes totaling 11,512 metres (HQ diameter)<br />

• July to October 2010: 22 holes for 4,676 metres (PQ diameter)<br />

The goal of <strong>the</strong> drilling was to c<strong>on</strong>tinue to delineate z<strong>on</strong>es of REE and Ta mineralizati<strong>on</strong>. The<br />

initial drilling (2007-2008) was completed largely at a spacing of approximately 150 m by 150 m.<br />

Eleven tightly-spaced inclined holes (L08-099 to L08-109) were drilled to obtain a mini-bulk<br />

sample for c<strong>on</strong>tinued metallurgical work <strong>on</strong> REE-enriched z<strong>on</strong>es. Six of <strong>the</strong> earlier holes were<br />

also re-assayed to test for <strong>the</strong> full suite of REE as was d<strong>on</strong>e <strong>on</strong> <strong>the</strong> recent drilling.<br />

Starting with <strong>the</strong> February 2009 program, <strong>the</strong> drill spacing was reduced and this resulted in<br />

intercepts at approximately 50 m centres. This spacing also allowed <strong>the</strong> resource estimate to<br />

be upgraded from Inferred to Indicated Resources as recommended in <strong>the</strong> Wardrop <str<strong>on</strong>g>report</str<strong>on</strong>g><br />

(March 2009). This drilling also focused <strong>on</strong> <strong>the</strong> south-eastern part of <strong>the</strong> <strong>deposit</strong> where <strong>the</strong><br />

Basal Z<strong>on</strong>e has higher TREO grades but also higher HREO grades (al<strong>on</strong>g with thicker<br />

intercepts). There was also an emphasis <strong>on</strong> utilizing drill setups for multiple intercepts of <strong>the</strong><br />

Basal Z<strong>on</strong>e in order to reduce drill moves, generate more structural informati<strong>on</strong> by intersecting<br />

Technical Report 43-101 – March 13, 2011 Page 11-1<br />

Prepared by Aval<strong>on</strong> Rare Metals Inc.