Thor Lake Surface<br />

The Thor Lake surface costs include <strong>the</strong> operati<strong>on</strong> and maintenance of <strong>the</strong> camp and surface<br />

facilities (but not <strong>the</strong> power house) and <strong>the</strong> operati<strong>on</strong> of <strong>the</strong> surface equipment for <strong>the</strong><br />

maintenance of roads and movement of materials and supplies excluding <strong>the</strong> summer barge lift<br />

costs and <strong>the</strong> associated handling of c<strong>on</strong>centrate, fuel and freight. The annual Thor Lake<br />

surface budget is shown in Table 18-43.<br />

Table 18-43 Surface Plant Costs<br />

Aval<strong>on</strong> Rare Metals Inc. – Thor Lake Project<br />

1,000 tpd 2,000 tpd<br />

C$ pa C$ pa<br />

Water Supply 24,000 36,000<br />

Sewage 6,000 60,000<br />

Heating System 60,000 84,000<br />

Plant Services 182,034 225,968<br />

Safety and First Aid 12,000 60,000<br />

Plant Operati<strong>on</strong> – Labour 2,633,297 2,844,855<br />

Plant Supervisi<strong>on</strong> 572,051 572,051<br />

Small Tools 12,000 12,000<br />

Building and Installati<strong>on</strong>s 18,000 60,000<br />

Heavy Equipment 120,000 180,000<br />

Light Vehicles 12,000 60,000<br />

Access Road Maintenance 9,000 60,000<br />

Air Strip and Site Road Maintenance 60,000<br />

Camp Operati<strong>on</strong>s 30,000 60,000<br />

Compressors 12,000 24,000<br />

O<strong>the</strong>r 57,264 60,856<br />

Total 3,759,647 4,459,730<br />

Cost per t<strong>on</strong>ne $10.30 $6.11<br />

Thor Lake Administrati<strong>on</strong><br />

The administrative costs for <strong>the</strong> Thor Lake site cover <strong>the</strong> mine site administrati<strong>on</strong> <strong>on</strong> <strong>the</strong> basis<br />

that <strong>the</strong> operati<strong>on</strong> is a stand al<strong>on</strong>e site with site management, purchasing, payroll and accounts<br />

payable handled by site pers<strong>on</strong>nel. Health and safety and envir<strong>on</strong>ment are also included in <strong>the</strong><br />

mine administrati<strong>on</strong>. The administrative cost estimate is summarized in Table 18-44.<br />

Technical Report 43-101 – March 13, 2011 Page 18-124<br />

Prepared by Aval<strong>on</strong> Rare Metals Inc.